Arizona Cancer Center, IT Closet Upgrade

Description

This project is to upgrade the IT Closets in the building and upgrade the infrastructure system within the building.

Project Number
13-9198
Building Number(s)
222
Current Budget
$165,000
Projected Ultimate Budget
$165,000
Project Manager
Construction Project Manager
Construction Schedule
July 2013 - September 2013
Contractor
Sturgeon Electric
Phase
Completed
Design Professional
UA PDC
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE