PROJECT INFORMATION

Parking Lot Improvements 2013

Description

Yearly parking lot improvements including the re-paving and re-sealing of miscellaneous existing lots.

Project Number
13-9203
Building Number(s)
Current Budget
$304,712
Projected Ultimate Budget
$304,712
Project Manager
Construction Project Manager
Construction Schedule
June 2013 - July 2013
Contractor
KE & G
Phase
Completed
Design Professional
KE & G
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE

Please try viewing in landscape mode.