34th Street Warehouse Renovation, Phase I

Description

Phase One interior renovation of a portion of the 34th St Warehouse to facilitate the relocation of UA PAC's and UITS operations from their current 22nd St Warehouse location. Future phases will address renovation of the balance of the facility as funding is secured to house or warehouse other University units.

Project Number
15-9251
Building Number(s)
370
Current Budget
$1,031,420
Projected Ultimate Budget
$1,031,420
Project Manager
Construction Project Manager
Construction Schedule
April 2015 - June 2015
Contractor
W. E. O'Neil
Phase
Completed
Design Professional
Sears Gerbo Architecture
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE