PROJECT INFORMATION

Administration Building, 4th Floor Remodel SAEM

Description

The department of Student Affairs & Enrollment Management (SAEM) is currently occupying half of the 4th Floor. The remodel will consolidate their operations located elsewhere on campus into the entire 4th floor by creating additional offices and support spaces, including the remodel of the elevator lobby/restroom core area.

Project Number
15-9261
Building Number(s)
66
Current Budget
$1,225,000
Projected Ultimate Budget
$1,225,000
Project Manager
Construction Project Manager
Construction Schedule
April 2016 - July 2016
Contractor
Division II Construction
Phase
Completed
Design Professional
Line and Space Architects
Delivery Method
Job Order Contract
GSF
3,850
VIEW SCHEDULE