Lowell-Stevens Football Facility (Az Stadium, North End Zone Expansion)

Description

Construction of the new north end-zone facility at Arizona Stadium will provide upgraded premium seating and fan amenities, relocate and provide new facilities for the football program and provide new concourses cross connecting access to the east and west stadium seating sections.

Status

Project is approximately 86% complete. Structural framing and exterior enclosure metal wall panels and glass now mostly complete. Roofing and deck water proofing complete. Interior wall and floor finishes underway on levels 1,2 and 3. MEP rough-in continuing on levels 4 and 5. Start up and commissioning of lighting, fire alarm and HVAC systems now underway on level 3. Exterior site work has started.

Project Number 09-8902 Building Number(s) 58E
Phase Construction Design Manager Vos, Bill
Delivery Method CMR Const. Manager Dolan, Brian
Projected Ultimate Budget $72,300,000
Projected Budget

The Budget represents a forecast of all costs related to the project that currently may not be fully funded or approved. For additional information about a specific project, click on the Project name displayed on the Project List
Design Professional Heery International Inc
Size 183,683 gross sq. ft.
140,589 net sq. ft.
Contractor Mortenson Construction
Const. Schedule December 2011 - July 2013