Description
Extension of the existing south end zone seats to replace bleachers (Red Zone) removed to install the new video board. Project also includes the restoration of the turf field for the 2012 season.
| Project Number |
12-9130 |
Building Number(s) |
58
|
| Phase |
Occupancy |
Design Manager |
Vos, Bill |
| Delivery Method |
CMR |
Const. Manager |
Dolan, Brian |
| Projected Ultimate Budget |
$1,742,207
|
Design Professional |
None |
| Size |
0 gross sq. ft.
0 net sq. ft. |
Contractor |
Mortenson Construction |
| Const. Schedule |
February 2012 - July 2012 |
|
|
|