PROJECT INFORMATION

North Campus Infrastructure

Description

North Campus Infrastructure was a multi-stage, multi-element project which expanded the University's existing infrastructure including, but not limited to mechanical; electrical; telecommunications utility distribution systems; central plant heating, chilled water and potable water production; sewer and surface drainage to support the new Bioscience Research Lab Building, the proposed Applied Sciences building and future campus growth.

Project Number
12-9135
Building Number(s)
N/A | 205
Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Construction Project Manager
Construction Schedule
January 2015 - May 2016
Contractor
Sundt Construction Inc
Phase
Finished
Design Professional
G L H N Architects And Engineers
Delivery Method
CMR
GSF
0
VIEW SCHEDULE

Please try viewing in landscape mode.