PROJECT INFORMATION

Hillenbrand Softball Lapan Family Center

Description

Based on the 2013 Feasibility Study and current donations, a Phase 1 project has been identified for Hillenbrand Softball. The project will include renovations and a additions to the batting cages This addition will include a team lounge, locker room with restrooms and shower, training room and an equipment storage room.

Project Number
13-9187
Building Number(s)
93E | 98
Current Budget
$1,552,000
Projected Ultimate Budget
$1,552,000
Project Manager
Construction Project Manager
Construction Schedule
August 2014 - February 2015
Contractor
Concord General Contracting
Phase
Completed
Design Professional
Swaim Associates Ltd AIA
Delivery Method
Job Order Contract
GSF
6,912