PROJECT INFORMATION

Health Sciences Innovation Building

Description

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

Status

East side concrete floor/roof structures are complete. Long span steel girders and decking are complete to the 9th floor. Concrete is being placed on the decking on the lower floors. East side curtain wall and terra cotta installation will begin soon. Interior wall framing underway on lower floors. Secure corridor construction to MRB is progressing.

Project Number
13-9193
Building Number(s)
216
Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Facilities Project Manager
Construction Schedule
June 2016 - July 2018
Contractor
Kitchell
Phase
Construction
Design Professional
CO Architects
Delivery Method
CMR
GSF
226,000
VIEW SCHEDULE

Please try viewing in landscape mode.