PROJECT INFORMATION

Parking Lot Improvements 2016

Description

Parking Lot 4054 located at 1519 E. First Street is currently an unpaved lot with eleven parking spaces in need of drainage, grading and paving improvements. The project will remedy serious potholes, ponding, windblown dust, erosion and traffic control issues.

Project Number
16-9322
Building Number(s)
Current Budget
$33,000
Projected Ultimate Budget
$33,000
Project Manager
Construction Project Manager
Construction Schedule
June 2016 - July 2016
Contractor
KE&G
Phase
Completed
Design Professional
Planning Design and Construction
Delivery Method
Job Order Contract
GSF
6,875
VIEW SCHEDULE