PROJECT INFORMATION

ICA Hi Corbett Renovations

Description

Upgrades to the Wildcat Baseball facility feature a new Terry Francona Hitting Facility and renovations to the team clubhouse and locker room. The more visible improvements in the stadium include the replacement of some spectator seating and a new backstop netting system .

Design Intent

This facililty will help to recruit the type of baseball players that the UA values. The hitting facility is all turf, has four batting cages, a full-sized bunting practice area and four turf mounds to help pitchers adjust to playing on turf fields. It's open at all times of day for players to go in and use, and is 100% climate controlled.

Project Number
17-9344
Building Number(s)
335
Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Construction Project Manager
Construction Schedule
January 2017 - October 2017
Contractor
Concord General Contracting
Phase
Completed
Design Professional
Breckenridge Group
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE