PROJECT INFORMATION

UAHS Building 201 Renovations

Description

As part of the University of Arizona/Banner Health initiative, a number of UAHS departments need to be relocated. To facilitate this phased relocation effort, existing space on multiple levels in Building 201 will be renovated to provide the administrative and ancillary support associated with UAHS departments.

Status

Contractor is mobilizing on site.

Project Number
17-9363
Building Number(s)
201
Current Budget
$14,500,000
Projected Ultimate Budget
$14,500,000
Project Manager
Facilities Project Manager
Construction Schedule
January 2018 - April 2018
Contractor
None
Phase
Construction
Design Professional
None
Delivery Method
Design/Build
GSF
0
VIEW SCHEDULE