PROJECT INFORMATION

Parking Lot Improvements 2017

Description

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8178 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Project Number
17-9364
Building Number(s)
Current Budget
$676,000
Projected Ultimate Budget
$676,000
Project Manager
Facilities Project Manager
Construction Schedule
May 2017 - December 2017
Contractor
Eagle Rock Excavating and McCarthy
Phase
Occupancy
Design Professional
Eagle Rock and DFDG/GLHN
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE