Parking Lot Improvements 2017

Description

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8178 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Status

Phase 1 - Lots 2152, 5073 and 5067 have been re-paved, striped and opened. The single one way bike path for east bound bike traffic along the south side of 5067 is completed and in use. Lots 8178 / 8179 have been expanded and opened. The pedestrian walkway between 6th and 7th Streets on the east side of Sitton Field is open and in use. Phase 2 - Design of Lot 3140 is finalized ready for construction to start.

Project Number
17-9364
Building Number(s)
Current Budget
$676,000
Projected Ultimate Budget
$676,000
Project Manager
Facilities Project Manager
Construction Schedule
May 2017 - December 2017
Contractor
Eagle Rock Excavating and McCarthy
Phase
Construction
Design Professional
Eagle Rock and DFDG/GLHN
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE