PROJECT INFORMATION

School of Arts Letterpress Program Relocation

Description

Evaluate potential relocation sites for the University's Fine Arts Letter Press Program.

Status

Phase 1 renovation work is nearing completion. Phase 2 renovation work will start in May 2018.

Project Number
17-9378
Building Number(s)
197
Current Budget
$425,000
Projected Ultimate Budget
$425,000
Project Manager
Facilities Project Manager
Construction Schedule
September 2017 - July 2018
Contractor
W. E. O'Neil
Phase
Construction
Design Professional
GLHN
Delivery Method
Job Order Contract
GSF
5,200
VIEW SCHEDULE