PROJECT INFORMATION

Hillenbrand Aquatic Center Improvements

Description

The Hillenbrand Aquatic Center Swimming Pool, Pump/Filtration Room and Chemical Room is due for a life cycle replacement. The pools structural integrity is severely degraded and the mechanical filtration system is corroded and unsafe. The new pool will not only be significantly longer (70m) but will have state-of-the-art technology for practicing and for competition. The pool will also accommodate multiple bulkheads. The Old Dive Pool will be demolished to create the space needed for the longer pool.

Status

Fee negotiations with top ranked D-B firm is ongoing.

Project Number
18-9388
Building Number(s)
096.01 | 96.01 | 96A
Current Budget
$25,000
Projected Ultimate Budget
$15,000,000
Project Manager
Facilities Project Manager
Construction Schedule
May 2018 - December 2018
Contractor
CORE Construction, Inc.
Phase
Design
Design Professional
Architekton
Delivery Method
Design/Build
GSF
29,000
VIEW SCHEDULE