PROJECT INFORMATION

Al Marah Equine Surgical Facility

Description

As part of the College of Veterinary program, existing facilities were renovated to provide equine treatment.

Project Number
18-9403
Building Number(s)
Current Budget
$303,500
Projected Ultimate Budget
$303,500
Project Manager
Construction Project Manager
Construction Schedule
January 2019 - May 2019
Contractor
Kapp-Con Inc dba TBR Construction
Phase
Completed
Design Professional
G L H N Architects And Engineers
Delivery Method
Job Order Contract
GSF
2,000
VIEW SCHEDULE