PROJECT INFORMATION

Andrew Weil Center for Integrative Medicine

Description

This project will develop a new facility for the Andrew Weil Center for Integrative Medicine (AWCIM) to centralize their operations in a physical building and landscape environment that supports their philosophy of healthy work environments.

Status

Main Office Building, Multi-purpose Building and Meditation Building are substantially complete. Furniture and AV systems install underway. Landscape is nearing completion with final touches to plants and drainage basins. Punch list completion and commissioning in progress.

Project Number
19-9472
Building Number(s)
233
Current Budget
$23,000,000
Projected Ultimate Budget
$23,000,000
Project Manager
Construction Project Manager
Construction Schedule
May 2022 - March 2024
Contractor
DPR Construction
Phase
Construction
Design Professional
Line and Space, LLC
Delivery Method
CMR
GSF
29,400
VIEW SCHEDULE