17-9369

1700 E. Broadway Building 480 Refurbishment/Repair

Refurbish and repair this 2-story office building to provide administrative space that will facilitate the phased relocation of UAHS departments.

Design Phase construction documents compete. GMP pricing underway.

Current Budget
$1,152,000
Projected Ultimate Budget
$1,152,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Dave Diebold Architect
Construction Schedule
July 2017 - September 2017
Contractor
W.E. O’Neil Construction Co.

16-9340

655 N. Alvernon Building 491 Refurbishment/Repair/Renovation

This project will refurbish/repair/renovate this building as required to provide administrative space that will facilitate the relocation of University of Arizona Health Sciences programs.

Design Phase construction documents in progress. Demolition has started. GMP pricing underway.

Current Budget
$4,995,000
Projected Ultimate Budget
$4,995,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Swaim Associates, LTD
Construction Schedule
July 2017 - November 2017
Contractor
KappCon Construction

17-9368

AME Building Room N341 Renovation

Renovation of Lab N341 to house a Mach 4 wind tunnel.

Cost proposal submitted - additional funding will be required

Current Budget
$100,000
Projected Ultimate Budget
$195,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
PD&C
Construction Schedule
August 2017 - December 2017
Contractor
Sun Mechanical

55-4033

Arid Lands Fiber Optic Feed Install

This project is to obtain a legal easement for a new overhead fiber optic data cable to the existing Arid Lands Studies building #184 located east of the Corner of 6th Street and Campbell from the UITS Building.

The survey and design is complete. Plans are being submitted for permit to City of Tucson.

Current Budget
$16,950
Projected Ultimate Budget
$16,950
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Dibble & Associates
Construction Schedule
TBD - TBD
Contractor
None

16-9316

Arizona Public Media - Renovations

Renovation of the radio operations wing of the AZPM broadcasting facility with the intent of upgrading and increasing production studio space. This part of the project was delivered in two phases in order to reduce disruptions to broadcast operations during construction. Phase Three includes improvements to the Televisions Master Control Room and minor millwork improvements.

Phase I and 2 of the radio operations renovation is completed and occupied. The design and pricing for Phase 3, the Television Master Control Room, is completed and work has started.

Current Budget
$592,000
Projected Ultimate Budget
$592,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
UA Planning Design & Construction
Construction Schedule
September 2016 - September 2017
Contractor
CORE Construction

77-9073

ASM Roland Basketry Gallery Remodel

Phase 3 of the Arizona State Museum Basket Collection Space project to reconfigure existing exhibit space in Room 102 to create the Arnold and Doris Roland Basketry Gallery. The Gallery project will provide much needed public access, display, education and interpretive space for the Arizona State Museum's Basket Collection, recipient of the Save America's Treasures Award. The State Museum seeks enhanced exhibit display performance criteria and a new design approach to better meet the museum's functional and budgetary requirements.

Current Budget
$472,000
Projected Ultimate Budget
$472,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Line and Space
Construction Schedule
October 2016 - March 2017
Contractor
Kappcon

17-9342

Biological Science West, Page & Peti Group Renovation

Modify laboratory spaces on the fifth floor of Bio West to provide research space for the Page and Peti Research groups

Current Budget
$650,000
Projected Ultimate Budget
$650,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
B W S -Burns Wald-Hopkins Shambach Architects
Construction Schedule
December 2016 - February 2017
Contractor
Division II Construction Co Inc

17-9345

Biological Science West, Rm 201 & 203 Renovation

Remodel Room 201 and 203 to support 3 NMR's. This project will create a core facility to support research.

Current Budget
$355,000
Projected Ultimate Budget
$355,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
January 2017 - March 2017
Contractor
Division II

14-9230

Biomedical Sciences Partnership Building

This facility is located on the Phoenix Biomedical Campus and includes research space, wet and dry laboratories, and related core facilities.

Current Budget
$136,100,000
Projected Ultimate Budget
$136,100,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
December 2014 - January 2017
Contractor
D P R / Sundt (A Joint Venture)

12-9134

Bioscience Research Laboratories

The BSRL will provide research facilities to support interdisciplinary research in many health science disciplines. This new facility will encourage collaborative translational research that will advance understanding of the molecular basis of human health, aging and disease.

Installation of mechanical, electrical, and plumbing systems is nearing completion on all levels. Sheetrock and painting are moving forward. The building exterior envelope work is underway with glass installation nearing completion, and brickwork moving quickly through all levels. The site hardscape and landscaping will begin soon. And finish cabinetry and audio visual system installation is underway.

Current Budget
$107,500,000
Projected Ultimate Budget
$107,500,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Zimmer Gunsul Frasca Architects, LLP
Construction Schedule
December 2015 - December 2017
Contractor
D P R Construction Inc

16-9337

BSRL Basement Shell Tenant Improvement

This project will build out shell space in the basement of the new BSRL building for Health Sciences CGRI instrumentation equipment.

Design is complete, and the construction phase has begun. The contractor has completed the foundations, and materials are in procurement. Walls are being framed and above ceiling work has begun.

Current Budget
$4,500,000
Projected Ultimate Budget
$4,500,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
ZGF Architects with BWS
Construction Schedule
December 2016 - December 2017
Contractor
DPR Construction

15-9273

C.A.T.S. Academic Center

The Arizona Wildcat Academic Center provides tutoring and other academic support services for all UA student athletes. The project also includes two polar plunge pools for athlete's conditioning and muscle recovery following workouts. The building is currently in use while exterior modifications are made to the front of the building.

Project is substantially complete and occupied. Added exterior metal panel work is also complete. Back check of punch list and project closeout is underway.

Current Budget
$7,550,000
Projected Ultimate Budget
$7,550,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
AECOM Technical Services
Construction Schedule
February 2016 - August 2017
Contractor
Mortenson Construction

16-9315

Chemical Sciences Building Rm 313 and Marvel Rm 414 Lab Remodel

Renovation of existing labs to accommodate a move from Old Chemistry Building into labs in Marvel and Chemical Sciences.

Current Budget
$230,000
Projected Ultimate Budget
$230,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
September 2016 - November 2016
Contractor
RW Burkel

16-9341

College of Law, Grand Staircase Display

In recognition of Richard D. Grand contributions, the College of Law is naming their main (grand) staircase in his honor. The project will construct a Memorial Exhibit Case that will house Richard D. Grand memorabilia.

Pre-Construction Meeting scheduled for 7/26/17. Construction Notice to Proceed will be issued 7/27/17.

Current Budget
$80,800
Projected Ultimate Budget
$89,800
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Gould Evans
Construction Schedule
July 2017 - August 2017
Contractor
Division II

16-9334

COM-Phoenix (Administration) Bldg 3002, Eller Administrative Suite Remodel

Remodel of 2nd floor east half of Building 1 on the Phoenix Biomedical Campus to accommodate new administrative offices for Eller Executive and Evening MBA programs.

Current Budget
$615,292
Projected Ultimate Budget
$615,292
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
SmithGroupJJR
Construction Schedule
September 2016 - December 2016
Contractor
DL Withers

16-9335

Computer Center Building 73, Room 236 Renovation

Renovate existing space in Room 236 to accommodate the relocation of Social and Behavioral Sciences technical personnel.

Current Budget
$375,000
Projected Ultimate Budget
$375,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Dave Diebold Architect
Construction Schedule
October 2016 - December 2016
Contractor
Concord General Contracting

55-2944

DAS Arizona Stadium Antenna Upgrades

Expansion of the Distributed Antenna System (DAS) in Arizona Stadium is being conducted in three stages or components. This component involves the relocation and expansion of antennas in Arizona Stadium

Work is underway and will be complete for 2017 football season

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Boingo
Construction Schedule
May 2017 - August 2017
Contractor
EWS

55-2942

DAS Expansion (Boingo) at Arizona Stadium

Expansion of the Distributed Antenna System (DAS) in Arizona Stadium is being conducted in three stages or components. This component involves the expansion of the head end equipment room and associated infrastructure improvements by Boingo.

work is underway and will be complete for 2017 football season.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Boingo
Construction Schedule
May 2017 - August 2017
Contractor
Boingo

55-2943

DAS Expansion (T-Mobile) at Arizona Stadium

Expansion of the Distributed Antenna System (DAS) in Arizona Stadium is being conducted in three stages or components. This component involves the fit out of new equipment by T-Mobile in the expanded head space.

Work is underway and will be complete for 2017 football season.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Boingo
Construction Schedule
May 2017 - August 2017
Contractor
EWS

03-8526

Environment & Natural Resources 2 (ENR2)

This new facility at 1064 E. Lowell St.(ENR2) east of the DeConcini ENRB1 furthers interdisciplinary research in earth, environmental, natural resources, math and related sciences. Included are faculty offices, conferencing, support spaces with related research/instructional dry laboratories and work space. A large classroom auditorium meets the critical need to teach an increasing number of students.

Current Budget
$75,000,000
Projected Ultimate Budget
$75,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
June 2013 - May 2015
Contractor
Hensel Phelps Construction Company

16-9294

Flandrau Science Center, Planetarium Theater Renovation

The Planetarium at Flandrau Science Center is receiving upgrades to the interior finishes of the theater. The upgrades include new seats, a revised seating configuration, paint, carpeting, wall finishes, and ADA upgrades.

Current Budget
$318,000
Projected Ultimate Budget
$318,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Dave Diebold Architect
Construction Schedule
June 2016 - August 2016
Contractor
Concord Construction

13-9182

Health Science Education Building, Finish Shell Space

This Tenant Improvement project in the Health Sciences Education Building will include a regional Simulation Center, completion of a Lecture Hall, administrative space, a Presidential Suite and the possible inclusion of classroom/Learning Studio space. Projects 13-9182 (HSEB, Finish Shell Space), 13-9206 (HSEB Finish Shell Space UA), and 13-9207 (HSEB Finish Shell Space NAU) will be covered under this description.

Current Budget
TBD
Projected Ultimate Budget
$17,900,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
January 2014 - July 2014
Contractor
None

09-8900

Health Sciences Education Building

The building on the Phoenix Biomedical Campus (PBC), 435 N. 5th Street, Phoenix 85004, includes flexible classrooms and state-of-the-art educational facilities, such as, simulation laboratories, gross anatomy facilities, preclinical training, learning resource center, student services and faculty office administrative space.

The HSEB creates an iconic identity for the University of Arizona School of Medicine on the Phoenix Biomedical Campus and responds to its urban locale and desert environment. The Arizona desert climate and need for reduced energy consumption informed much of the design, from the way the building is sited at its location to the type of fenestration and the innovative cooling methods used. Inspired by the iconic canyon formations found throughout Arizona, the façade reinterprets stratified earth layers revealed over time as a copper sunscreen protecting the exterior building enclosure from direct solar exposure. Akin to the natural forces that shape the Earth’s geology, the copper skin is fissured, formed, bent, pressed, and perforated, creating beauty from a functional building need. The architectural design promotes physical connectivity to the downtown Phoenix community with indoor and outdoor spaces that encourage interaction.

Current Budget
$135,998,801
Projected Ultimate Budget
$135,998,801
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
July 2010 - July 2012
Contractor
D P R / Sundt (A Joint Venture)

13-9193

Health Sciences Innovation Building

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

Stair and elevator cores are nearing completion to the 9th floor. East side concrete floor structures continue upward. Long span steel girders begin installation on July 24. Secure corridor construction to Skaggs and MRB is progressing. Basement framing and MEP rough-in are underway. Drachman Circle is being reconfigured. Final GMP 4 pricing has been formally added to the project.

Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
CO Architects
Construction Schedule
June 2016 - July 2018
Contractor
Kitchell

18-9388

Hillenbrand Aquatic Center Improvements

The Hillenbrand Aquatic Center Swimming Pool, Pump Room and Chemical Room is due for a life cycle replacement and will be extended to accommodate bulkheads. The Old Dive Pool will be demolished to create space for the Pool extension. A new score board will be installed.

ABOR multi-step approval process has commenced.

Current Budget
TBD
Projected Ultimate Budget
$15,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
April 2018 - December 2018
Contractor
None

17-9382

Hillenbrand Stadium Renovations

The project addresses renovations to the existing softball stadium include the following primary items: Sun shading, create new fan amenities in seating areas, press box renovations, upgrade dugouts, and replace backstop netting system.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Swaim
Construction Schedule
TBD - TBD
Contractor
None

14-9227

HSEB - NAU Occupational Therapy Area Improvements

Project consists of the remodel of the existing occupational therapy rooms in the Health Science Education Building to accommodate new equipment that is being purchased by Northern Arizona University.

Current Budget
$170,716
Projected Ultimate Budget
$170,716
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2014 - July 2014
Contractor
None

17-9344

ICA Hi Corbett Renovations

Upgrades to the baseball facilities include a new backstop netting system, replacing some of the spectator seating, and interior renovations to the team clubhouse and locker room. Project scope increased to now also include the new Terry Francona Hitting Facility.

Clubhouse locker room renovations underway and on schedule. Progress on the Terry Francona Hitting Facility has been impacted by lead paint removal and now summer rains. Working on several fronts to recover schedule.

Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Breckenridge Group
Construction Schedule
January 2017 - September 2017
Contractor
Concord General Contracting

18-9390

ICA Indoor Sports Center

A new building to provide safe all-weather practice for football and other sports. The multi-use facility is envisioned to benefit multiple sports which will also serve as a game day venue.

The Request for Qualifications for selection of a Design-Build team is in-progress.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

16-9309

Kuiper SEM/TEM Phase B

The goal of the expansion of the SEM/TEM Imaging Core is to accommodate two existing Hitachi SEMs presently located in the Marley Chemistry building, and future advanced technology imaging equipment. It will also provide interactive meeting space for researchers from the Lunar and Planetary Laboratory as well as visiting users from UA and industry partners. Specifically the expansion will achieve the following goals: Provide state of the art imaging capability to LPL, UA and outside users; Provide office space for technicians assigned to the Imaging Core; Provide a modular and flexible environment to allow for a variety of imaging instruments

Current Budget
$1,302,000
Projected Ultimate Budget
$1,302,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Sears Gerbo
Construction Schedule
September 2016 - January 2017
Contractor
R W Burkel

16-9299

Maricopa Agricultural Center, Install Field Gantry

This project involves the construction of a foundation system to support a 28m x 218.5m field scanner gantry instrument at the Maricopa Ag. Center. Project also includes the installation of main electrical and telecom service.

Current Budget
$620,000
Projected Ultimate Budget
$620,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Structural Concepts
Construction Schedule
October 2015 - March 2016
Contractor
Div. II Construction

17-9358

Maricopa Hall Renovations

Renovations to the nearly century old residence hall will include conversion of sleeping porches into student rooms, modifications to student room storage, replacement windows in lounges, installation of occupancy sensors, and replacement flooring in student rooms and corridors.

Current Budget
$1,890,000
Projected Ultimate Budget
$1,890,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
May 2017 - August 2017
Contractor
Lloyd Construction

17-9343

Marvel 5th Floor Lab Renovation

Renovate portions of the fifth floor of Marvel to provide research space for the Marty research Group.

Current Budget
$250,000
Projected Ultimate Budget
$250,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
January 2017 - March 2017
Contractor
W. E. O'Neil

17-9360

McClelland Hall Lab 214 Renovation

In order to enhance the teaching delivery and, improve the learning experience, the Eller College of Management is renovating McClelland Hall Lab 214 by converting the tiered lecture style seating into a flexible Classroom space with mediated interaction.

Demolition phase is underway

Current Budget
$831,000
Projected Ultimate Budget
$831,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Gould Evans
Construction Schedule
June 2017 - September 2017
Contractor
Division II

13-9191

McKale Memorial Center Improvements

The original approved $80 million project for the improvements at the McKale Memorial Center will be moving forward as phased projects. The first phase will be a $29.9 million project that consists of two parts. Project 14-9222 has been identified for equipment procurement and installation of the wood gym floor and arena seating. Project 13-9191 consists of aisle tread improvements, hand railing, additional ADA platforms, locker room improvements, a vertical circulation tower (stair and elevator), additional restrooms and concessions at the concourse level.

Current Budget
$25,000,000
Projected Ultimate Budget
$80,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
AECOM Technical Services
Construction Schedule
April 2014 - June 2016
Contractor
Mortenson Construction

18-9385

McKale Memorial Center, Locker Room Suite 170 Remodel

In order to improve student athlete support areas, Intercollegiate Athletics (ICA) is remodeling multiple locker rooms and adding a new locker room complete with lounge/team areas, kitchenette, etc.

Fee negotiations with top ranked Design Professional firm is complete.

Current Budget
$300,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Swaim Associates, Ltd
Construction Schedule
December 2017 - August 2018
Contractor
Concord General Contracting

55-2963

Mt. Lemmon OWL Telescope

Steward Observatory has requested PDC's assistance in facilitating the installation of a new enclosure to house a new 0.5M OWL telescope. Project is privately funded and will be operated by the Korean Astronomy Space Sciences Institute (KASI).

Current Budget
$5,754
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design & Construction
Construction Schedule
February 2016 - November 2016
Contractor
Kappcon

16-9323

Multiple Parking Garage Maintenance Repairs 2017

In 2013, a "Conditions Evaluation and Preventative Maintenance Report" was issued for all of the parking garages on Campus including the Highland Avenue, Park Avenue, Tyndall Avenue, Sixth Street, and Main Gate Garages. This project will address all of the needs that were identified in that report to repair and maintain these five garages in 2017. The actual repairs and maintenance will be done in the summer of 2017. This work will assure that these five garages are maintained in good condition and remain serviceable for the foreseeable future.

Maintenance and repairs to Highland Ave., Park Ave., Main Gate, Tyndall Ave. and 6th Street Garages are in progress. Work includes replacement of caulking, repair of expansion joints and repainting stairs.

Current Budget
$700,000
Projected Ultimate Budget
$700,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Desman Associates
Construction Schedule
May 2017 - August 2017
Contractor
None

12-9135

North Campus Infrastructure

North Campus Infrastructure is a multi-stage, multi-element project which will expand the University's existing infrastructure including, but not limited to mechanical; electrical; telecommunications utility distribution systems; central plant heating, chilled water and potable water production; sewer and surface drainage to support the new Bioscience Research Lab Building, the proposed Engineering Innovation Building and future campus growth.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2015 - May 2016
Contractor
Sundt Construction Inc

16-9322

Parking Lot Improvements 2016

Parking Lot 4054 located at 1519 E. First Street is currently an unpaved lot with eleven parking spaces in need of drainage, grading and paving improvements. The project will remedy serious potholes, ponding, wind blown dust, erosion and traffic control issues.

Current Budget
$33,000
Projected Ultimate Budget
$33,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Planning Design and Construction
Construction Schedule
June 2016 - July 2016
Contractor
KE&G

17-9364

Parking Lot Improvements 2017

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8173 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Lots 2152, 5073 and 5067 have been re-paved, striped and opened. A single lane one way bike path for east bound bike traffic is being installed through Lot 5067. Lot 3140 is on hold pending review of its future use as a service permit or visitor lot. Work on the expansion and improvement to lots 8173 / 8179 will start soon.

Current Budget
$612,000
Projected Ultimate Budget
$612,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
tbd
Construction Schedule
May 2017 - August 2017
Contractor
tbd

16-9320

Phoenix Biomedical Campus Classroom Renovations

Classroom upgrades to install power at the tables and upgrade AV systems in the classrooms in the Health Science Education Building on the Phoenix Biomedical Campus. Work will involve installing floor boxes, and modifying furniture arrangement to maximize the use of the classroom space to accommodate the expanding programs of College of Medicine - Phoenix, Nursing, and Pharmacy.

Current Budget
$162,650
Projected Ultimate Budget
$162,650
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2016 - July 2016
Contractor
Cannon & Wendt

18-9391

Pima County Court House, Gem and Mineral Museum Relocation

Explore the feasibility of the relocation of the UA Gem and Mineral Museum to the Old Pima County Courthouse. Level 0 (Basement) 7,000sf - Research Lab, Community and Storage Level 1 (Main Level) 11,100sf- Gem and Mineral Museum Exhibits.

Project is pending Administrative review. Pima County is reviewing the space planning.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Pima County (Poster Frost Mirto)
Construction Schedule
January 2018 - October 2018
Contractor
Pima County

17-9378

School of Arts Letterpress Program Relocation

Evaluate potential relocation sites for the University's Fine Arts Letter Press Program.

Concept design is being estimated.

Current Budget
$425,000
Projected Ultimate Budget
$425,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
GLHN
Construction Schedule
TBD - TBD
Contractor
W. E. O'Neil

08-8847

Solar/Sustainable Initiatives

A solar/sustainable initiative is underway that is being facilitated through the University's partnership with AMERESCO to advance solar technology awareness on campus and throughout the community. Through this initiative solar installations are planned for Second Street Garage, Student Recreation Center, McClelland Hall, McClelland Park, Hillenbrand Aquatic Center, Red Rock Ag Center, Campus Ag Center, Controlled Environmental Ag Center, West Campus Ag Center, Ville Del Puente Res Hall, and Posada San Pedro Res Hall.

Current Budget
$235,500
Projected Ultimate Budget
$235,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
AMERESCO
Construction Schedule
July 2009 - July 2012
Contractor
AMERESCO

13-9168

South Stadium Parking Structure

This five-level parking structure with 915 parking spaces will be conveniently located south of 6th Street near student housing and athletic facilities. The UA has sold all available permits for campus parking spots and has established a growing waiting list for parking permits. The 6th St. & Warren Ave. intersection has been redesigned to align with National Championship Drive to the north and will include a traffic signal which is expected to greatly improve traffic flow throughout the area and increase efficiency and safety. Sidewalks and bike lanes will be added along Warren Ave.

Slabs on grade at Level 1 and all four levels of suspended slabs are completed. Crash walls and bases for future level columns are nearing completion. The cast-in-place double elevator shaft is completed up to the penthouse and related masonry veneer and glazing are nearing completion. The elevator installation is in progress. Medium voltage and communication cables have been pulled and terminated. Underground utilities are nearing completion. Grading for the re-alignment of Warren Avenue with National Championship Drive, and the adjacent parking lot is in progress.

Current Budget
$22,000,000
Projected Ultimate Budget
$22,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
DFDG
Construction Schedule
December 2016 - August 2017
Contractor
McCarthy Building Companies

17-9376

Southwest Center, Building 375, 375A & 375B Repairs

The College of Social and Behavioral Sciences intends to conduct roofing repairs and remedial work on these three buildings which are part of their Southwest Center program.

Roof repairs are complete. Interior ceiling repairs are in progress.

Current Budget
$250,000
Projected Ultimate Budget
$250,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
June 2017 - August 2017
Contractor
None

16-9321

Student Recreation Center, Locker Room Remodel

This is a comprehensive locker room remodel to achieve greater inclusivity for all Recreation Center patrons, as well as update the 25 year old facilities with more contemporary design features and finishes.

Elevator and stairs complete. Locker room light fixtures, plumbing trim, interior painting and tile finishes underway. Exterior masonry and site work ongoing.

Current Budget
$4,945,000
Projected Ultimate Budget
$4,945,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Breckenridge Group
Construction Schedule
March 2017 - August 2017
Contractor
Lloyd Construction

17-9381

Student Success District

Student Affairs/Enrollment Management & Academic Initiatives/ Student Success (SAEM/AISS) and University Libraries have collaborated to create a Student Success District, an integrative approach to supporting student achievement by weaving together revitalized services in upgraded facilities. The intent of creating this district is to improve student success through direct connections between student services, academic support, and amenities in the heart of campus near other important student centered activities. When fully realized, the Student Success District will be a distinctive element of the UA experience, supporting student engagement and playing an important role in attracting and retaining students. This strategic initiative includes these physical facilities improvements: • renovations and additions to Bear Down Gym • renovations and entry addition to the Main Library • renovations to the Science-Engineering Library • redevelopment of adjacent exterior areas into student focused outdoor environments • new linkages between buildings The project includes two phases of construction. Phase One will be an addition the Bear Down Gym and an addition to, and remodeling of portions of the Main Library. The Bear Down Gym addition will be located on the south of the building and will likely house student services. Phase Two will include renovations to Bear Down Gym as well as improvements to the Science Library and open space between Bear Down Gym and the two Library buildings.

Programming phase is underway.

Current Budget
$3,000,000
Projected Ultimate Budget
$71,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Poster Frost Mirto
Construction Schedule
July 2018 - June 2020
Contractor
Sundt

17-9353

Student Union Memorial Center, Chick-fil-A Relocation

In order to improve student food services, the Student Union Memorial Center is renovating by upgrading and expanding the food space for Chick-fil-A .

Demolition is complete. New framing and MEP rough-in are underway. Finishes will begin installation. New and reconditioned kitchen equipment are arriving for installation.

Current Budget
$500,000
Projected Ultimate Budget
$500,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Merry Carnell Schlecht
Construction Schedule
July 2017 - September 2017
Contractor
CORE Construction

55-2899

SUMC Optical Company Tenant Improvements

This is a tenant improvement being primarily completed by the Student Union with help from FM. The tenant is also doing a small amount of finish work with their own contractor. PDC is providing oversight and inspection.

SUMC/FM work is complete. Tenant has constructed office walls and installed front counter. Painting and wall base are underway before move-in.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
June 2017 - August 2017
Contractor
None

55-2898

SUMC Steak and Shake Tenant Improvements

This is a tenant improvement project. MSE Branded Foods is a SUMC tenant who is constructing a Steak N' Shake Restaurant in the old Burger King space. They have contracted with WE O'Neil to complete this work. PDC is providing oversight and inspection.

Framing and MEP rough-in are underway. Old exhaust hoods are being removed and new ones installed.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
July 2017 - August 2017
Contractor
None

15-9264

SUMC-Bookstore, Room 202 Remodeling

Remodel the main level to update the facility to better serve customers and to reflect the current retail marketing trends.

Current Budget
$1,000,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Colkitt & Co Architects
Construction Schedule
May 2016 - July 2016
Contractor
W.E. O'Neil Construction Co. Inc.

10-9001

UA Cancer Center-Phoenix - Phase I

This new facility will provide the highest quality cancer research and care with an evidence-based, multi-disciplinary model, along with the modern technologies, and a compassionate patient-centered approach. The building will be located at 625 N. 6th St, on the northwest corner of Fillmore and Seventh Streets on the downtown Phoenix Biomedical Campus.

Current Budget
$100,000,000
Projected Ultimate Budget
$100,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsel Frasca
Construction Schedule
January 2013 - May 2015
Contractor
Hensel Phelps Construction Co.

16-9339

UAHS Border Health, Building 426 Renovation

Renovation of leased building to provide office and clinic space to accommodate the UAHS Border Health Initiative program in Nogales, Arizona.

Current Budget
$485,000
Projected Ultimate Budget
$485,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Dave Diebold Architect
Construction Schedule
January 2017 - February 2017
Contractor
Lloyd Construction Co., Inc.

16-9313

UITS Infrastructure Upgrade

This project is to upgrade the existing IT Data Network Hubs for a systems upgrade to 100GB network.

Current Budget
$297,000
Projected Ultimate Budget
$297,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design and Construction
Construction Schedule
March 2016 - May 2016
Contractor
Sturgeon ELectric

17-9365

University Services Building 3rd Floor Renovation

Renovation of existing Office Space on the 3rd floor NE corner of USB Building 158 to convert into a functional space for University Analytics & Institutional Research operations.

Mechanical, electrical, and plumbing rough in work is underway. Wall framing is complete. And drywall is scheduled to begin shortly.

Current Budget
$695,000
Projected Ultimate Budget
$695,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Dave Diebold Architects
Construction Schedule
June 2017 - September 2017
Contractor
D L Withers

55-4032

USA East Parking Lot / 6th Street Underpass

The Downtown Links project that the City of Tucson is constructing for the 6th Street underpass of the Union Pacific Railroad will require the realignment of the entrance to the east parking lot and a new parking lot layout which includes new parking lot lighting.

Design of the parking lot lighting and relocation of the gate operators are complete. Construction to begin Summer 2016.

Current Budget
$3,731
Projected Ultimate Budget
$4,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
UA Planning Design & Construction
Construction Schedule
TBD - TBD
Contractor
None