18-9389

655 N Alvernon Building 491 FFE Procurement and Installation

Office furnishings for the various occupant groups.

Current Budget
$1,005,000
Projected Ultimate Budget
$1,005,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Swaim Associates
Construction Schedule
TBD - TBD
Contractor
N/A

16-9340

655 N. Alvernon Building 491 Refurbishment/Repair/Renovation

Refurbish/repair/renovate this off-campus building as required to provide administrative space for University of Arizona Health Sciences programs that will be relocating from the UAHS medical campus as part of the UA/Banner University Medical Center initiative.

Current Budget
$4,995,000
Projected Ultimate Budget
$4,995,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Swaim Associates, LTD
Construction Schedule
July 2017 - May 2018
Contractor
KappCon Construction

18-9403

Al Marah Equine Surgical Facility

As part of the College of Veterinary program, existing facilities are being renovated to provide equine treatment.

Contractor is mobilized and construction is in progress.

Current Budget
$303,500
Projected Ultimate Budget
$303,500
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2019 - March 2019
Contractor
Kapp-Con Inc dba TBR Construction

19-9447

AME Room N229 Supersonic Wind Tunnel Installation

Facility modifications of new wind tunnel in AME .

DP proposal in preparation. .

Current Budget
$495,000
Projected Ultimate Budget
$495,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

19-9440

AME, Medical Device Maker/Lab Remodel

Convert existing space on level 1 of AME into a maker/lab space for the Medical Device Design Experience.

Construction Documents are underway - JOC estimate is being prepared.

Current Budget
$1,000,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Affiliated Engineers Inc
Construction Schedule
March 2019 - July 2019
Contractor
None

18-9386

Applied Research Building

The new facility is envisioned to be an approximate 60,000 GSF multi-story building with a mix of space tpes including high bay areas, varying types of laboratories, clean rooms, faculty offices, and conference rooms.

The Request for Qualifications for Design/Build Teams has started and advertised.

Current Budget
$600,000
Projected Ultimate Budget
$50,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
May 2020 - July 2021
Contractor
None

16-9330

Arizona Stadium Renovation

A feasibility study was completed, evaluating the cost and impact of renovating the east, west and south sides of the Arizona football stadium including improving the infrastructure, safety, code upgrades, circulation, restrooms, concessions and fan amenities. As a result, the initial phase of renovation is on the east side of the stadium, including work on the ground level concourse (including new concessions and restrooms), student seating area (the ZonaZoo), and the southeast entrance.

Substantial completion achieved for all areas. Punch list work underway.

Current Budget
$25,463,000
Projected Ultimate Budget
$150,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
J E Dunn w/ Populous & Swaim
Construction Schedule
January 2018 - September 2018
Contractor
J E Dunn Construction Company

14-9230

Biomedical Sciences Partnership Building

This facility is located on the Phoenix Biomedical Campus and includes research space, wet and dry laboratories, and related core facilities.

Current Budget
$136,100,000
Projected Ultimate Budget
$136,100,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
December 2014 - January 2017
Contractor
D P R / Sundt (A Joint Venture)

12-9134

Bioscience Research Laboratories

The BSRL will provide research facilities to support interdisciplinary research in many health science disciplines. This new facility will encourage collaborative translational research that will advance understanding of the molecular basis of human health, aging and disease.

Current Budget
$107,500,000
Projected Ultimate Budget
$107,500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsul Frasca Architects, LLP
Construction Schedule
December 2015 - February 2018
Contractor
D P R Construction Inc

16-9337

BSRL Basement Shell Tenant Improvement

This project will build out shell space in the basement of the new BSRL building for Health Sciences CGRI instrumentation equipment.

Current Budget
$4,500,000
Projected Ultimate Budget
$4,500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
ZGF Architects with BWS
Construction Schedule
December 2016 - February 2018
Contractor
DPR Construction

18-9416

CALS Tucson Village Farm

Construct a new building approximately 1,950 GSF / 1,600 NASF for the College of Agriculture and Life Sciences (CALS) and the Pima County Cooperative Extension to house a certified teaching kitchen space for educational programming, support spaces, and an outdoor patio.

Progressing with construction documents and construction pricing

Current Budget
$442,000
Projected Ultimate Budget
$442,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Vint & Associates Architects, Inc.
Construction Schedule
February 2019 - June 2019
Contractor
R. W. Burkel Contracting, Inc.

19-9468

CAPLA Addition and Renovation

CAPLA has recently completed the pre-design Programming that is aligned with the College's overall Strategic Plan, with the goal being to improve space utilization and provide academic facilities that will enhance learning and support the growth of academic programs. CAPLA would now like a review of the Master Plan, a re-configuration of the entire space planning as Programmed and developing a full Schematic Design of the entire existing CAPLA West building and may incorporate parts of CAPLA East Building. The first phase of the project will then be identified. Future phases will be contingent on the availability of funds.

RFQ for Design Professional Services is about to be advertised.

Current Budget
TBD
Projected Ultimate Budget
$2,450,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
January 2020 - May 2020
Contractor
None

18-9397

CAPLA West, 2nd and 3rd Floor Remodel

In order to improve space utilization and provide facilities for increased program growth, CAPLA plans to reconfigure the current CAPLA West spaces for improved efficiency with a view to increase student studio and research spaces and also provide active learning and collaborative classrooms.

Programming, Master planning and Phasing diagrams are complete.

Current Budget
$100,000
Projected Ultimate Budget
$100,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Line and Space
Construction Schedule
TBD - TBD
Contractor
None

19-9472

Center for Integrative Medicine

A new facility for the Arizona Center for Integrative Medicine (CIM) that will facilitate the fundamental goal of creating a physical environment that supports the philosophy of integrative medicine.

Project is under UA administrative review.

Current Budget
$25,000
Projected Ultimate Budget
$25,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

18-9390

Cole and Jeannie Davis Sports Center

The new building, located at the old Sancet Stadium site and current outdoor practice fields, will provide safe all-weather practice for football and other sports. The multi-use facility is envisioned to benefit multiple sports and could also possibly serve as an additional game day venue.

Building roof almost complete. Interior synthetic turf and graphics package underway. Exterior site work also underway.

Current Budget
$16,300,000
Projected Ultimate Budget
$16,300,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
BWS & HOK
Construction Schedule
April 2018 - February 2019
Contractor
M. A. Mortenson Company

19-9454

College of Law, Class Lab 126 and 146 Renovation

In order to improve the Trial Advocacy learning experience, the College of Law will be renovating Class Labs 126 and 146 into a single large Mock Courtroom.

Programming is near completion.

Current Budget
$27,000
Projected Ultimate Budget
$27,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Smithgroup
Construction Schedule
TBD - TBD
Contractor
None

16-9341

College of Law, Grand Staircase Display

In recognition of Richard D. Grand contributions, the College of Law is naming their main (grand) staircase in his honor. The project will construct a Memorial Exhibit Case that will house Richard D. Grand memorabilia.

Current Budget
$89,800
Projected Ultimate Budget
$89,800
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Gould Evans
Construction Schedule
July 2017 - December 2017
Contractor
Division II

17-9362

College of Pharmacy Skaggs Building Addition and Renovation

This project will provide the College of Pharmacy with both new and renovated state-of-the-art research lab facilities to ensure its growth and capacity to adapt to the dynamic and changing fields in pharmaceutical sciences. The College of Pharmacy intends to continue its innovation and excellence in research, practice and education and make a substantial impact on improving the health of people of Arizona and around the world. A new two-story addition will house biology and chemistry research labs. A separate smaller addition will display items from the Pharmacy Museum collection. Some existing building areas will be renovated, including research labs and administrative offices.

Construction is in full swing with the foundations complete and the steel structure in place. Design of the museum addition is also nearing completion. and renovation of existing interior spaces has begun. And the project is on schedule for at later fall substantial completion.

Current Budget
$26,000,000
Projected Ultimate Budget
$26,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
G L H N Architects And Engineers
Construction Schedule
September 2018 - November 2019
Contractor
DPR Construction

19-9439

College Of Veterinary Medicine Facilities Support

To facilitate the provision of the necessary practical, clinical skills and pathology education required, the College of Veterinary Medicine is constructing new and renovating existing facilities at West Campus Agricultural Center (WCAC) and Campus Agricultural Center (CAC) sites.

WCAC construction drawings are being reviewed.

Current Budget
$60,000
Projected Ultimate Budget
$60,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
March 2019 - May 2019
Contractor
None

16-9334

COM-Phoenix (Administration) Bldg 3002, Eller Administrative Suite Remodel

Remodel of 2nd floor east half of Building 1 on the Phoenix Biomedical Campus to accommodate new administrative offices for Eller Executive and Evening MBA programs.

Current Budget
$615,292
Projected Ultimate Budget
$615,292
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
SmithGroupJJR
Construction Schedule
September 2016 - December 2016
Contractor
DL Withers

55-2946

DAS Mckale Memorial Center

This project involves the installtion of a distributed antenna system (DAS) within McKlae Memorial Center to improve cell service during events.

Project has commenced and is underway.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
May 2018 - October 2018
Contractor
None

19-9427

Education Building, Room 104 Renovation

The College of Education (COE) will create a multipurpose Digital Innovation and Learning Lab (DIALL) that will extend research capacity and offer opportunities for K-12 students, pre-service teachers, and COE faculty to collaboratively explore activities such as producing digital media, creating digital stories, exploring gaming interfaces, learning coding skills, accessing online information, creating podcasts, designing stop-motion animation shorts, and exploring programming.

Schematic Design is near completion.

Current Budget
$75,000
Projected Ultimate Budget
$75,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

19-9448

Education North, Room 110 & 111 Renovation

In order to grow their outreach programs, the College of Education and the College of Humanities are partnering to renovate existing Seminar Rooms 110/111 to better serve the University outreach mission and also create a stronger connection with the Schaefer Poetry Center.

Programming is complete. Conceptual design is ongoing.

Current Budget
$25,000
Projected Ultimate Budget
$25,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Line and Space
Construction Schedule
TBD - TBD
Contractor
None

18-9423

ENR II Rooftop Solar Installation

Installation of Photovoltaic panels and roof top gardens.

Planter layout received - design documents started

Current Budget
$510,000
Projected Ultimate Budget
$510,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
G L H N Architects And Engineers
Construction Schedule
TBD - TBD
Contractor
None

18-9384

Grand Challenges Research Building

The Grand Challenges research building will be an interdisciplinary facility providing new wet and dry laboratory space for growth of research programs. The building is envisioned to be a nine floor building located on the main campus.

This project is in the pre-planning phase.

Current Budget
TBD
Projected Ultimate Budget
$135,100,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
May 2021 - November 2023
Contractor
None

13-9182

Health Science Education Building, Finish Shell Space

This Tenant Improvement project in the Health Sciences Education Building will include a regional Simulation Center, completion of a Lecture Hall, administrative space, a Presidential Suite and the possible inclusion of classroom/Learning Studio space. Projects 13-9182 (HSEB, Finish Shell Space), 13-9206 (HSEB Finish Shell Space UA), and 13-9207 (HSEB Finish Shell Space NAU) will be covered under this description.

Current Budget
TBD
Projected Ultimate Budget
$17,900,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
January 2014 - July 2014
Contractor
None

09-8900

Health Sciences Education Building

The building on the Phoenix Biomedical Campus (PBC), 435 N. 5th Street, Phoenix 85004, includes flexible classrooms and state-of-the-art educational facilities, such as, simulation laboratories, gross anatomy facilities, preclinical training, learning resource center, student services and faculty office administrative space.

The HSEB creates an iconic identity for the University of Arizona School of Medicine on the Phoenix Biomedical Campus and responds to its urban locale and desert environment. The Arizona desert climate and need for reduced energy consumption informed much of the design, from the way the building is sited at its location to the type of fenestration and the innovative cooling methods used. Inspired by the iconic canyon formations found throughout Arizona, the façade reinterprets stratified earth layers revealed over time as a copper sunscreen protecting the exterior building enclosure from direct solar exposure. Akin to the natural forces that shape the Earth’s geology, the copper skin is fissured, formed, bent, pressed, and perforated, creating beauty from a functional building need. The architectural design promotes physical connectivity to the downtown Phoenix community with indoor and outdoor spaces that encourage interaction.

Current Budget
$135,998,801
Projected Ultimate Budget
$135,998,801
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
July 2010 - July 2012
Contractor
D P R / Sundt (A Joint Venture)

13-9193

Health Sciences Innovation Building

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

Substantial Completion punchlist inspections are nearing completion. Life Safety inspections by State Fire Marshall are underway. Furniture and AV installations are nearing completion. Misc. interior finish work is wrapping up. West exterior metal skin is being installed. Site work and hardscape are progressing .

Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
CO Architects
Construction Schedule
June 2016 - February 2019
Contractor
Kitchell

18-9388

Hillenbrand Aquatic Center Improvements

The Hillenbrand Aquatic Center Swimming Pool, Pump/Filtration Room and Chemical Room is due for a life cycle replacement. The pools structural integrity is severely degraded and the mechanical filtration system is corroded and unsafe. The new pool will not only be significantly longer (70m) but will have state-of-the-art technology for practicing and for competition. The pool will also accommodate multiple bulkheads. The Old Dive Pool will be demolished to create the space needed for the longer pool.

Current Budget
$13,250,000
Projected Ultimate Budget
$13,250,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Architekton
Construction Schedule
April 2018 - December 2018
Contractor
CORE Construction, Inc.

17-9382

Hillenbrand Softball Stadium Renovations

The project will renovate portions of the existing softball stadium including the following primary items: sun shading, new loge and standing areas, press box renovations, upgrade dugouts, replace the backstop netting system, and new restrooms and concessions.

Completion of Punch list underway.

Current Budget
$8,000,000
Projected Ultimate Budget
$8,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Swaim Associates
Construction Schedule
June 2018 - February 2019
Contractor
Concord General Contracting

14-9227

HSEB - NAU Occupational Therapy Area Improvements

Project consists of the remodel of the existing occupational therapy rooms in the Health Science Education Building to accommodate new equipment that is being purchased by Northern Arizona University.

Current Budget
$170,716
Projected Ultimate Budget
$170,716
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2014 - July 2014
Contractor
None

18-9393

La Aldea Residence Hall Renovations

The apartment units in the Graduate Housing facility will be renovated, including finishes, casework and fixtures.

Current Budget
$1,225,000
Projected Ultimate Budget
$1,225,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Breckenridge Group
Construction Schedule
March 2018 - August 2018
Contractor
Lloyd Construction

18-9401

Main Library, 4th and 5th Level Relocations

Renovation to portions of the 1st & 4th Level pods of the Main Library to accommodate reorganization of library staff. Phase 1 renovations include areas on the 1st & 4th Level of Main Library and a portion of the 1st Level of Science Engineering Library. 5th Level Renovations and upgrades to toilet rooms on 3rd, 4th & 5th Level of the Main Library are anticipated for Phase 2.

Construction is underway. Two phases of construction renovation are planned: Phase 1 - inside the Main and Science Libraries has begun and will continue thru April 2019, Phase 2 - will occur Summer of 2020.

Current Budget
$2,500,000
Projected Ultimate Budget
$2,500,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Gould Evans Architects
Construction Schedule
December 2018 - April 2019
Contractor
Core Construction

18-9413

Maricopa Agricultural Center, Install Field Gantry Phase II

Original project was competed in 2016 and this Phase 2 project will now extend the rails for the field scanner gantry north 175.6M (576.1') and complete associated extensions to the power, lightning protection, telecom, irrigation, fencing and security systems.

Current Budget
$500,000
Projected Ultimate Budget
$500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Structural Concepts
Construction Schedule
June 2018 - January 2019
Contractor
Division II Construction

18-9404

Marvel Labs Rm 506,514,550,554 Renovation

Renovate 4 lab modules to be suitable for organic Chemistry in support a relocation from old chemistry

General construction mostly complete waiting for Lab casework delivery

Current Budget
$1,000,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Sears Gerbo Architecture
Construction Schedule
October 2018 - February 2019
Contractor
R. W. Burkel

18-9385

McKale Memorial Center, Locker Room Suite 170 Remodel

In order to improve student athlete support areas, Intercollegiate Athletics (ICA) will be adding 4 new locker rooms and remodeling 2 existing locker rooms. The remodeled spaces will be complete with lounge/team areas, kitchenette, etc.

Current Budget
$1,900,000
Projected Ultimate Budget
$1,900,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Swaim Associates, Ltd
Construction Schedule
April 2018 - August 2018
Contractor
Concord General Contracting

19-9433

Mirror Lab Storage Rack

Provide a racking system to facilitate the safe and secure storage of three 8.4 meter mirrors.

Rack design is in progress.

Current Budget
$41,125
Projected Ultimate Budget
$41,125
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
M3 Engineering
Construction Schedule
December 2018 - January 2019
Contractor
None

16-9323

Multiple Parking Garage Maintenance Repairs 2017

In 2013, a "Conditions Evaluation and Preventative Maintenance Report" was issued for all of the parking garages on Campus including the Highland Avenue, Park Avenue, Tyndall Avenue, Sixth Street, and Main Gate Garages. This project will address all of the needs that were identified in that report to repair and maintain these five garages in 2017. The actual repairs and maintenance will be done in the summer of 2017. This work will assure that these five garages are maintained in good condition and remain serviceable for the foreseeable future.

Current Budget
$700,000
Projected Ultimate Budget
$700,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Desman Associates
Construction Schedule
May 2017 - October 2007
Contractor
Core Construction

12-9135

North Campus Infrastructure

North Campus Infrastructure is a multi-stage, multi-element project which will expand the University's existing infrastructure including, but not limited to mechanical; electrical; telecommunications utility distribution systems; central plant heating, chilled water and potable water production; sewer and surface drainage to support the new Bioscience Research Lab Building, the proposed Engineering Innovation Building and future campus growth.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2015 - May 2016
Contractor
Sundt Construction Inc

17-9349

Oro Valley Veterinary Medicine Facility

The Oro Valley Veterinary Medicine Facility will be the administrative and pre-clinical training headquarters for the University of Arizona's College of Veterinary Medicine program. This project will provide the renovations and equipment to facilitate the necessary programmatic areas to support student teaching, learning and hands-on experience.

Strategic demolition is in progress in preparation for the renovation.

Current Budget
$8,000,000
Projected Ultimate Budget
$8,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
GLHN
Construction Schedule
December 2018 - May 2019
Contractor
Lloyd Construction Co Inc

17-9364

Parking Lot Improvements 2017

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8178 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Current Budget
$676,000
Projected Ultimate Budget
$676,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Eagle Rock and DFDG/GLHN
Construction Schedule
May 2017 - December 2017
Contractor
Eagle Rock Excavating and McCarthy

18-9410

Parking Lot Improvements 2018

Pave and stripe Lots 7102, 5083 and 5072. Seal coat and stripe Lots 7103, 2029, 7156 and 7228. Landscape Lots 7102, 7103 and 2030.

Current Budget
$700,000
Projected Ultimate Budget
$1,030,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
PD&C
Construction Schedule
June 2018 - July 2019
Contractor
Ashton Company Inc The

18-9425

PBC ABC1 4th Floor Lab Remodel

Remodel of an existing chemical fume hood area into a tissue culture room on the 4th floor of the Arizona Biomedical Collaborative Building 1. Work involves removing existing chemical fume hoods, and installing biosafety cabinets in its place. Work also involves relocating doors, repairing finishes, and adjusting air balance.

This project is substantially complete.

Current Budget
$113,000
Projected Ultimate Budget
$113,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
SmithGroup
Construction Schedule
TBD - TBD
Contractor
McCarthy Building Companies

18-9396

PBC, NW Corner of 7th St and Pierce St, Development, Demolition & Site Prep

Feasibility study for the single family houses, duplex and the commercial property on the Phoenix Biomedical Campus.

Demolition for existing commercial building, and the two single family houses has been completed. Study is ongoing for duplex property.

Current Budget
$275,000
Projected Ultimate Budget
$275,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

19-9449

Phoenix BSPB 3rd & 4th Floor Finish Shell Space

The fit out of the 3rd and 4th floor shell space of Biomedical Sciences Partnership Building into additional wet lab space on the Phoenix Biomedical Campus.

Preliminary internal meetings for programming are being scheduled.

Current Budget
$1,500,000
Projected Ultimate Budget
$34,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

18-9391

Pima County Court House, Gem and Mineral Museum Relocation

Explore the feasibility of the relocation of the UA Gem and Mineral Museum to the Old Pima County Courthouse. Lower Level 9,200sf - Research Lab, Community and Storage Level 1 (Main Level) 11,700sf- Gem and Mineral Museum Exhibits.

Tenant Improvement Construction Documentation near publication. Exhibit Design is ongoing.

Current Budget
$100,000
Projected Ultimate Budget
$100,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Pima County (Poster Frost Mirto)
Construction Schedule
February 2019 - March 2020
Contractor
Pima County (Design&Production, Inc.)

18-9408

Roy Place Renovations

Construction of toilet rooms, along with other building system upgrades and building modernization for tenant improvements on the 1st and 2nd floors.

Design Development is nearing completion with anticipation of moving to Construction Documents phase.

Current Budget
$1,000,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Merry Carnell Schlecht Inc.
Construction Schedule
March 2019 - June 2019
Contractor
Barker Contracting, Inc.

17-9378

School of Arts Letterpress Program Relocation

Relocate the University's Fine Arts Letter Press Program across Mabel Street into the Visual Arts Grad Lab (Bldg. No. 197). The new Honors College is consuming the site of the old Letter Press studio.

Current Budget
$425,000
Projected Ultimate Budget
$425,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
September 2017 - July 2018
Contractor
W. E. O'Neil

08-8847

Solar/Sustainable Initiatives

A solar/sustainable initiative is underway that is being facilitated through the University's partnership with AMERESCO to advance solar technology awareness on campus and throughout the community. Through this initiative solar installations are planned for Second Street Garage, Student Recreation Center, McClelland Hall, McClelland Park, Hillenbrand Aquatic Center, Red Rock Ag Center, Campus Ag Center, Controlled Environmental Ag Center, West Campus Ag Center, Ville Del Puente Res Hall, and Posada San Pedro Res Hall.

Current Budget
$460,500
Projected Ultimate Budget
$460,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
AMERESCO
Construction Schedule
July 2009 - July 2012
Contractor
AMERESCO

13-9168

South Stadium Parking Structure

This five-level parking structure with 915 parking spaces is conveniently located south of 6th Street near student housing and athletic facilities. The 6th St. & Warren Ave. intersection was redesigned to align with National Championship Drive to the north and includes a new traffic signal, sidewalks and bike lanes which are expected to greatly improve traffic flow throughout the area and increase efficiency and safety.

Current Budget
$22,000,000
Projected Ultimate Budget
$22,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
DFDG
Construction Schedule
December 2016 - August 2017
Contractor
McCarthy Building Companies

19-9450

South Stadium Rowhouses

This CAPLA student design-build project will provide new faculty/staff temporary housing. Six proposed rowhouses will be located along Seventh Street, adjacent to the South Stadium Parking Garage. The rowhouses are planned to be constructed one at a time, phased over seven years.

Construction of the first rowhouse unit is underway.

Current Budget
$50,000
Projected Ultimate Budget
$50,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
CAPLA
Construction Schedule
February 2019 - December 2019
Contractor
CAPLA

17-9376

Southwest Center, Building 375, 375A & 375B Repairs

The College of Social and Behavioral Sciences intends to conduct roofing repairs and remedial work on these three buildings which are part of their Southwest Center program.

Current Budget
$516,500
Projected Ultimate Budget
$516,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2017 - July 2018
Contractor
Lloyd Construction Co Inc

16-9321

Student Recreation Center, Locker Room Remodel

This is a comprehensive locker room remodel to achieve greater inclusivity for all Recreation Center patrons, as well as update the 25 year old facilities with more contemporary design features and finishes.

Current Budget
$4,945,000
Projected Ultimate Budget
$4,945,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Breckenridge Group
Construction Schedule
March 2017 - August 2017
Contractor
Lloyd Construction

17-9381

Student Success District

The new Student Success District will integrate and revitalize student services in four adjacent central campus buildings: Main Library, Weaver Science-Engineering Library, Bear Down Gym, and a new Student Services Building. The project will also include site development improvements.

Construction is underway on site utilities and the Main Library. Construction of the Weaver Science-Engineering Library is anticipated to begin this spring. Design phase is in process for the Student Success Building and Bear Down Gym.

Current Budget
$81,000,000
Projected Ultimate Budget
$81,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Poster Frost Mirto
Construction Schedule
January 2019 - October 2021
Contractor
Sundt

55-2898

SUMC Steak and Shake Tenant Improvements

This is a tenant improvement project. MSE Branded Foods is a SUMC tenant who is constructing a Steak N' Shake Restaurant in the old Burger King space. They have contracted with WE O'Neil to complete this work. PDC is providing oversight and inspection.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
July 2017 - August 2017
Contractor
None

18-9399

SUMC, Room 226A Starbucks Remodel

In order to improve student food service and retail experience, UA Bookstores will be reconfiguring and expanding the existing Starbucks shop.

Current Budget
$440,000
Projected Ultimate Budget
$440,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Merry Carnell Schlecht (MCS)
Construction Schedule
July 2018 - July 2018
Contractor
CORE Construction, Inc.

10-9001

UA Cancer Center-Phoenix - Phase I

This new facility provides the highest quality cancer research and care with an evidence-based, multi-disciplinary model, along with the modern technologies, and a compassionate patient-centered approach. The building is located at 625 N. 6th St, on the northwest corner of Fillmore and Seventh Streets on the downtown Phoenix Biomedical Campus.

Current Budget
$100,000,000
Projected Ultimate Budget
$100,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsel Frasca
Construction Schedule
January 2013 - May 2015
Contractor
Hensel Phelps Construction Co.

18-9395

UA Honors Village

The University of Arizona has entered into a Public Private Partnership agreement with American Campus Communities to develop, design and construct the UA Honors Village, a multi-building complex consisting of a 1035 bed Honors Dorm, that also includes academic space and food services, a Recreation Center and a 4 story, 370 space Parking Structure.

Construction is progressing well on all three buildings and all are on schedule.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
STG Architects
Construction Schedule
November 2017 - July 2019
Contractor
Okland Construction

15-9286

UAHS BSPB 10th Floor Finish Shell Space

Fit out of Level 10 in BSPB for new administrative offices for the College of Medicine Phoenix.

Final interior finishes are being installed. Ceiling grid and wood ceiling panels are nearing completion. Final paint has started. Flooring installation is complete.

Current Budget
$8,550,000
Projected Ultimate Budget
$8,550,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
CO Architects
Construction Schedule
June 2018 - December 2018
Contractor
D P R / Sundt (A Joint Venture)

17-9363

UAHS Building 201 Renovations

As part of the University of Arizona/Banner Health initiative, a number of UAHS departments need to be relocated. To facilitate this phased relocation effort, existing space on multiple levels in Building 201 will be renovated to provide the administrative and ancillary support associated with UAHS departments.

Current Budget
$14,500,000
Projected Ultimate Budget
$14,500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN Architects & Engineers
Construction Schedule
January 2018 - April 2018
Contractor
Lloyd Construction Co Inc

16-9313

UITS Infrastructure Upgrade

This project is to upgrade the existing IT Data Network Hubs for a systems upgrade to 100GB network.

Current Budget
$297,000
Projected Ultimate Budget
$356,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design and Construction
Construction Schedule
March 2016 - May 2016
Contractor
Sturgeon ELectric

55-4032

USA East Parking Lot / 6th Street Underpass

The Downtown Links project that the City of Tucson is constructing for the 6th Street underpass of the Union Pacific Railroad will require the realignment of the entrance to the east parking lot and a new parking lot layout which includes new parking lot lighting.

Design of the parking lot lighting and relocation of the gate operators are complete. Construction to begin Summer 2016.

Current Budget
$3,731
Projected Ultimate Budget
$4,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
UA Planning Design & Construction
Construction Schedule
TBD - TBD
Contractor
None