Intercollegiate Athletics Fac Additions & Renov

Description

Project is comprised of 3 distinct elements that will enhance the quality of training and competition facilities for several athletic programs. This is part of the ICA long-term plan to upgrade facilities as donor funding becomes available. Goals include enhancing training facilities and improving the ability to recruit top-level student athletes and coaches. The elements are an Indoor Practice Facility, Gymnastics Training Facility Expansion and Hillenbrand Aquatic Center Diving Pool.

Project Number 06-8676 Building Number(s) 140 | 96A | 96B
Phase Closed Design Manager Mackey, Rodney
Delivery Method CMR Const. Manager Dolan, Brian
Projected Ultimate Budget $20,000,000 Design Professional Breckenridge Group
Size 29,100 gross sq. ft.
20,449 net sq. ft.
Contractor Lloyd Construction Co Inc
Const. Schedule April 2007 - October 2008    
Projected Budget

The Budget represents a forecast of all costs related to the project that currently may not be fully funded or approved. For additional information about a specific project, click on the Project name displayed on the Project List