Lowell-Stevens Football Facility (Az Stadium, North End Zone Expansion)

Description

The new north end-zone facility at Arizona Stadium provides upgraded premium seating and fan amenities; new facilities for the football program; and new concourses cross connecting access to the east and west stadium seating sections.

Project Number 09-8902 Building Number(s) 58E
Phase Occupancy Design Manager Vos, Bill
Delivery Method CMR Const. Manager Dolan, Brian
Projected Ultimate Budget $72,300,000 Design Professional Heery International Inc
Size 183,683 gross sq. ft.
140,589 net sq. ft.
Contractor Mortenson Construction
Const. Schedule December 2011 - July 2013    
Projected Budget

The Budget represents a forecast of all costs related to the project that currently may not be fully funded or approved. For additional information about a specific project, click on the Project name displayed on the Project List