PROJECT INFORMATION

Hillenbrand Aquatic Center Improvements

Description

The Hillenbrand Aquatic Center Swimming Pool, Pump/Filtration Room and Chemical Room underwent a life-cycle replacement. The pools structural integrity was severely degraded and the mechanical filtration system was corroded and unsafe. The new pool is not only significantly longer (70m) but has state-of-the-art technology for practicing and for competition. The pool also accommodates multiple bulkheads. The Old Dive Pool was demolished to create the space needed for the longer pool.

Project Number
18-9388
Building Number(s)
096.01 | 96.01 | 96A | 96A
Current Budget
$13,250,000
Projected Ultimate Budget
$13,250,000
Project Manager
Construction Project Manager
Construction Schedule
April 2018 - December 2018
Contractor
CORE Construction, Inc.
Phase
Completed
Design Professional
Architekton
Delivery Method
Design/Build
GSF
31,000
VIEW SCHEDULE