PROJECT INFORMATION

SALT Center Renovation and Expansion

Description

Renovation and expansion of the SALT Center to support an increasing population of students to receive services that have proven to contribute to success and graduation of students with learning challenges.

Project Number
13-9204
Building Number(s)
136
Current Budget
$2,734,000
Projected Ultimate Budget
$2,734,000
Project Manager
Construction Project Manager
Construction Schedule
October 2015 - June 2016
Contractor
R.W. Burkell Contracting
Phase
Completed
Design Professional
Gould Evans Associates
Delivery Method
Job Order Contract
GSF
8,814
VIEW SCHEDULE