PROJECT INFORMATION

Grand Challenges Research Building

Description

GCRB is a new research facility that will leverage the University of Arizona's core strengths to address the grand challenges identified in Pillar 2 of the University's strategic plan. GCRB will be an interdisciplinary facility designed to foster conversations among sciences and programs. The 7-story building will be located on Cherry Avenue as part of the Wyant College of Optical Sciences complex. The new building will be south of Meynell West, and across the street from the Main Library. GCRB will support research laboratories for expansion of the Optical Sciences under the Office of the Provost to continue advancing the University's international reputation in this field, as well as new sponsored projects for the Office of Research Innovation and Impact. test

Status

Project is in construction phase. The structure is complete. The work on the building facade is also nearing completion. The interior construction has progressed from the basement through the 6 floor with framing, drywall, and MEP systems. The site utilities are getting tied-in and commissioned. And building finishes have begun on the lower levels.

Project Number
18-9384
Building Number(s)
126
Current Budget
$99,000,000
Projected Ultimate Budget
$99,000,000
Project Manager
Construction Project Manager
Construction Schedule
July 2021 - February 2024
Contractor
Kitchell Contractors, Inc. of Arizona
Phase
Construction
Design Professional
ZGF Architects/BWS Architects
Delivery Method
Design/Build
GSF
107,877
VIEW SCHEDULE