PROJECT INFORMATION

UAHS BSPB 2nd Floor Finish Shell Space

Description

Fit out of existing 2nd floor shell space in the Biomedical Sciences Partnership Building for interim space for UAHS Center for Advanced Molecular and Immunotherapies (CAMI) while planning continues for the new building.

Status

Finish trim is being installed in BSL3 lab. Punch list activities are underway on the 2nd floor.

Project Number
22-9586
Building Number(s)
3006
Current Budget
$18,500,000
Projected Ultimate Budget
$18,500,000
Project Manager
Construction Project Manager
Construction Schedule
March 2023 - April 2024
Contractor
DPR / Sundt (A Joint Venture)
Phase
Construction
Design Professional
CO Architects
Delivery Method
CMR
GSF
0
VIEW SCHEDULE