PROJECT INFORMATION

SUMC Building 19, Room 205 Remodeling

Description

This project remodels Room 205 in the Student Union Memorial Center to create a new restaurant concept that will feature bar food menu items as well as beer and wine. A small brewery will highlight the CALES master brewery program and produce beer on site that will be delivered directly to the new bar.

Status

Restaurant construction is complete. Brewery in construction phase. Awaiting delivery of brew equipment. Estimated completion of brewery is set for spring.

Project Number
22-9608
Building Number(s)
19
Current Budget
$1,400,000
Projected Ultimate Budget
$1,400,000
Project Manager
Construction Project Manager
Construction Schedule
April 2023 - May 2024
Contractor
WE ONeil Construction Company Inc
Phase
Construction
Design Professional
Multistudio, Inc.
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE

Please try viewing in landscape mode.