PROJECT INFORMATION

Arizona Stadium, Student Union Food Service Equipment

Description

Kitchen and serving area equipment design, purchase, and installation for the development of the the Cafe, Concessions and Loge/Club to be located in the Arizona Stadium North End-Zone Expansion. The food services will be owned and operated by the Student Union and will support Arizona Stadium during events as well as student athletes and the campus community during non game days.

Project Number
11-9071
Building Number(s)
58E
Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Construction Project Manager
Construction Schedule
November 2012 - July 2013
Contractor
Mortenson Construction
Phase
Completed
Design Professional
Heery International
Delivery Method
CMR
GSF
0
VIEW SCHEDULE