PROJECT INFORMATION

South Stadium Parking Structure

Description

This five-level parking structure with 915 parking spaces will be conveniently located south of 6th Street near student housing and athletic facilities. The UA has sold all available permits for campus parking spots and has established a growing waiting list for parking permits. The 6th St. & Warren Ave. intersection has been redesigned to align with National Championship Drive to the north and will include a traffic signal which is expected to greatly improve traffic flow throughout the area and increase efficiency and safety. Sidewalks and bike lanes will be added along Warren Ave.

Status

Construction is underway. Utility relocations, mass excavation, elevator pit, drilled piers, grade beams and cast-in-place columns are in progress. Designs for the Warren Avenue re-alignment and related egress features are being finalized.

Project Number
13-9168
Building Number(s)
138
Current Budget
$22,000,000
Projected Ultimate Budget
$22,000,000
Project Manager
Facilities Project Manager
Construction Schedule
December 2016 - August 2017
Contractor
McCarthy Building Companies
Phase
Construction
Design Professional
DFDG
Delivery Method
Design/Build
GSF
282,000
VIEW SCHEDULE