PROJECT INFORMATION

Health Sciences Innovation Building

Description

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

Status

Basement walls and columns are complete. South half of 1st floor concrete slab has been poured. North half of 1st floor is being formed and will be poured soon. Stair and elevator cores are being formed and poured above the 1st floor level. Secure corridor construction to Skaggs and MRB is progressing. Final construction documents were issued in late March for review and pricing.

Project Number
13-9193
Building Number(s)
216
Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Facilities Project Manager
Construction Schedule
June 2016 - July 2018
Contractor
Kitchell
Phase
Construction
Design Professional
CO Architects
Delivery Method
CMR
GSF
226,000
VIEW SCHEDULE