PROJECT INFORMATION

Phoenix Parking Lot 10002 Expansion

Description

Project consists of the expansion of the existing surface parking lot adjacent to Building 4 (UA Foundation Building) on the Phoenix Biomedical Campus. Approximately 65 new spaces will be added to support the Campus.

Project Number
13-9205
Building Number(s)
Current Budget
$250,000
Projected Ultimate Budget
$250,000
Project Manager
Construction Project Manager
Construction Schedule
June 2013 - August 2013
Contractor
D P R Construction Inc
Phase
Completed
Design Professional
None
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE

Please try viewing in landscape mode.