PROJECT INFORMATION

Applied Research Building

Description

The new Applied Research Building (ARB) is a very specialized, one of a kind research facility designed specifically for UA applied research programs. This three-story building has a variety of programmed spaces, including high bay payload assembly areas, a large scale thermal vacuum chamber, unique research / customized laboratories, clean rooms, faculty offices, collaboration spaces, and conference rooms. The ARB is located at the southeast corner of Helen Street and the Highland Corridor. The Highland Corridor has been improved and realigned as part of this project to provide safer pedestrian and bicycle crossings at Helen Street.

Project Number
18-9386
Building Number(s)
173
Current Budget
$85,000,000
Projected Ultimate Budget
$85,000,000
Project Manager
Construction Project Manager
Construction Schedule
June 2021 - March 2023
Contractor
McCarthy Building Companies
Phase
Occupancy
Design Professional
SmithGroup
Delivery Method
Design/Build
GSF
89,000
VIEW SCHEDULE

Please try viewing in landscape mode.