PROJECT INFORMATION

AME Hypersonic Wind Tunnel Complex Upgrades

Description

Augment the compressed air system to improve runtime of the AME Hypersonic wind tunnel

Status

Startup/commissioning is scheduled. Electrical service has been energized.

Project Number
22-9607
Building Number(s)
119
Current Budget
$3,730,000
Projected Ultimate Budget
$3,730,000
Project Manager
Construction Project Manager
Construction Schedule
September 2023 - June 2024
Contractor
T. D. Industires - Sturgeon Electric
Phase
Construction
Design Professional
GLHN
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE