PROJECT INFORMATION

Bryant Bannister Tree Ring Building – AMS Renovation

Description

Renovations to a portion of the 2nd floor area (Rooms 240A-F, 242, 244, 246, and library outreach area) at Tree Ring Archives Building #45 to create new laboratory space to house an Accelerator Mass Spectrometer procured through a National Science Foundation grant.

Status

Design Development phase is in progress. Working with stakeholders to refine scope of work and details.

Project Number
23-9671
Building Number(s)
45
Current Budget
$1,250,000
Projected Ultimate Budget
$1,250,000
Project Manager
Construction Project Manager
Construction Schedule
July 2024 - October 2024
Contractor
Kappcon General Contractors
Phase
Design
Design Professional
GLHN Architects Engineers, Inc.
Delivery Method
Job Order Contract
GSF
3,500
VIEW SCHEDULE