PROJECT INFORMATION

Visual Arts Graduate Research Laboratory renovation

Description

Reconfigure spaces inside the building to provide additional studios that can be assigned to graduate student, faculty and visiting artists. Enhanced presentation areas will also be created.

Status

Design Development is nearing completion.

Project Number
23-9639
Building Number(s)
197
Current Budget
$3,000,000
Projected Ultimate Budget
$3,000,000
Project Manager
Construction Project Manager
Construction Schedule
May 2024 - October 2024
Contractor
CORE Construction
Phase
Design
Design Professional
BWS Architects
Delivery Method
Job Order Contract
GSF
23,520
VIEW SCHEDULE