PROJECT INFORMATION

Chemistry Building Renovations

Description

This Strategic Plan initiative will renovate and repurpose the historic Chemistry Building, centrally located on the Mall, into an innovative teaching hub. Evidence-based teaching strategies (collaboration, inclusive practices, and active learning) result in increased student learning, engagement, and development of workplace-relevant skills. Deferred maintenance, life safety, accessibility, code upgrades, and sustainability will also be addressed.

Status

New build window frames are installed, glass in progress. Exterior metal panels are in progress. Renovated area brick restoration is in progress. The first elevator cab is installed. Magnetic shielding in the West NMR space is in progress. AHUs 1-3 are installed on roof. FFE ordered and expected in December. Phase 1 is Substantially Complete.

Project Number
19-9473
Building Number(s)
41
Current Budget
$42,000,000
Projected Ultimate Budget
$42,000,000
Project Manager
Construction Project Manager
Construction Schedule
May 2021 - December 2022
Contractor
Sundt Construction
Phase
Construction
Design Professional
Shepley Bulfinch
Delivery Method
Design/Build
GSF
78,600
VIEW SCHEDULE