16-9340

655 N. Alvernon Building 491 Refurbishment/Repair/Renovation

Refurbished/repaired/renovated this off-campus building as required to provide administrative space for University of Arizona Health Sciences programs that were relocated from the UAHS medical campus as part of the UA/Banner University Medical Center initiative.

Current Budget
$4,995,000
Projected Ultimate Budget
$4,995,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Swaim Associates, LTD
Construction Schedule
July 2017 - May 2018
Contractor
KappCon Construction

20-9507

Administration Building, 5th & 6th Floor Renovations

Remodel/Renovate existing space of the 5 & 6 floors to create a contemporary suite of flexible and collaborative offices that reflect the culture of the Office of the Provost and the Office of the Senior Vice President for Research & Innovation.

Preliminary design is in progress.

Current Budget
$135,000
Projected Ultimate Budget
$1,300,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
December 2019 - February 2020
Contractor
None

18-9403

Al Marah Equine Surgical Facility

As part of the College of Veterinary program, existing facilities were renovated to provide equine treatment.

Current Budget
$303,500
Projected Ultimate Budget
$303,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2019 - May 2019
Contractor
Kapp-Con Inc dba TBR Construction

19-9447

AME Room N229 Supersonic Wind Tunnel Installation

Facility modifications for new wind tunnel in AME .

JOC contractor preparing quote . Water line rerouting is scheduled.

Current Budget
$495,000
Projected Ultimate Budget
$495,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Sears Gerbo
Construction Schedule
September 2019 - February 2020
Contractor
R W Burkel

19-9440

AME, Medical Device Maker/Lab Remodel

Convert existing space on level 1 of AME into a maker/lab space for the Medical Device Design Experience.

Window wall installation has started. MEP trim is in process.

Current Budget
$1,300,000
Projected Ultimate Budget
$1,300,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Affiliated Engineers Inc
Construction Schedule
June 2019 - December 2019
Contractor
R. W. Burkel

19-9472

Andrew Weil Center for Integrative Medicine

A new facility for the Andrew Weil Center for Integrative Medicine (AWCIM). The Center will facilitate the fundamental goal of creating a physical environment that supports the philosophy of integrative medicine. The facility and its exterior spaces will house the following basic functions: Administrative, Clinical Simulation, Educational, Culinary Demonstrations and Meditation spaces. The Center will reflect a distinctive life-enhancing environment.

Conceptual Design is nearly complete. Fee negotiations with top ranked CM@Risk firm is nearly complete.

Current Budget
$3,000,000
Projected Ultimate Budget
$20,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Line and Space, LLC
Construction Schedule
September 2020 - September 2021
Contractor
None

18-9386

Applied Research Building

The new facility is envisioned to be an approximate 85,250 GSF multi-story building with a mix of space types including high bay areas, varying types of laboratories, clean rooms, faculty offices, and conference rooms.

This project is in the Schematic Design phase.

Current Budget
$6,100,000
Projected Ultimate Budget
$101,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
SmithGroup
Construction Schedule
June 2020 - May 2022
Contractor
McCarthy Building Companies

16-9330

Arizona Stadium Renovation

A feasibility study was completed, evaluating the cost and impact of renovating the east, west and south sides of the Arizona football stadium including improving the infrastructure, safety, code upgrades, circulation, restrooms, concessions and fan amenities. As a result, the initial phase of renovation was on the east side of the stadium, including work on the ground level concourse (including new concessions and restrooms), student seating area (the ZonaZoo), and the southeast entrance.

Current Budget
$25,463,000
Projected Ultimate Budget
$150,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
J E Dunn w/ Populous & Swaim
Construction Schedule
January 2018 - September 2018
Contractor
J E Dunn Construction Company

19-9464

Arizona Stadium, Scholarship Suites Renovations

Interior renovations (finishes, furniture & equipment) to the third level of the skybox suites.

Current Budget
$3,110,000
Projected Ultimate Budget
$3,110,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
HKS Inc.
Construction Schedule
May 2019 - August 2019
Contractor
DPR Construction

19-9485

Arizona Stadium, West Renovations

Initial planning process for the next Arizona Stadium renovations, including the west side

Working with consultant to collect and organize valuable feedback from Wildcat fans on what the future of Arizona Stadium will look like.

Current Budget
$400,000
Projected Ultimate Budget
$400,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Populous
Construction Schedule
TBD - TBD
Contractor
J E Dunn Construction Company

14-9230

Biomedical Sciences Partnership Building

This facility is located on the Phoenix Biomedical Campus and includes research space, wet and dry laboratories, and related core facilities.

Current Budget
$136,100,000
Projected Ultimate Budget
$136,100,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
December 2014 - January 2017
Contractor
D P R / Sundt (A Joint Venture)

12-9134

Bioscience Research Laboratories

The BSRL provides research facilities to support interdisciplinary research in many health science disciplines. This new facility encourages collaborative translational research that will advance understanding of the molecular basis of human health, aging and disease.

BSRL is the final puzzle piece that completes the master-plan for its urban block in the Health Sciences Campus. The original vision for a campus courtyard was initiated by the Keating BIO5 and MRB buildings, which frame the south, east, and north edges of the space. The BSRL building gives final definition to the courtyard by establishing its western edge while also providing access into it through a grand two-story opening. This breezeway portal gives passage to a mid-block pedestrian route and celebrates BSRL’s role as a gateway and a campus threshold. BSRL is a North-South bar building, and its simple form expresses both a sense of repose and dynamic movement as the bridge-like top story suspends itself above the central portal and stretches southward over the transparent, street-welcoming first story. The short north and south ends cantilever outwards to accentuate the street corners and emphasize the building as a gate-way to and from the UA bio-science campus along Cherry Avenue. As part of the three-building set, BSRL sympathizes with and expands the architectural vocabulary of Keating Bio5 and MRB. Like the two other buildings, BSRL has an outward-facing shell of red brick that provides the entire block with aesthetic consistency. This outer layer also acts as a protective shield to the more transparent, courtyard-facing inner layer. BSRL’s brick facade is lifted along the southern half of the western edge along Cherry Avenue, creating a more welcoming presence and a new front door to the complex. This exposes the glazed lobby and interaction space, which was conceived as an extension of the outdoor environment, joining the street realm and the inner courtyard through a layered, visually connected continuum of activity spaces: pedestrian colonnade, interaction lobby and café, and breezeway portal.

Current Budget
$107,500,000
Projected Ultimate Budget
$107,500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsul Frasca Architects, LLP
Construction Schedule
December 2015 - February 2018
Contractor
D P R Construction Inc

16-9337

BSRL Basement Shell Tenant Improvement

This project built out shell space in the basement of the new BSRL building for Health Sciences CGRI instrumentation equipment.

Current Budget
$4,500,000
Projected Ultimate Budget
$4,500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
ZGF Architects with BWS
Construction Schedule
December 2016 - February 2018
Contractor
DPR Construction

18-9416

CALS Tucson Village Farm

Renovations of the Karsten Turfgrass Research Facility for the College of Agriculture and Life Sciences (CALS) and the UA Cooperative Extension to house a certified teaching kitchen space for educational programming and support spaces.

Demolition is underway

Current Budget
$558,000
Projected Ultimate Budget
$558,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
GLHN
Construction Schedule
November 2019 - February 2020
Contractor
R. W. Burkel Contracting, Inc.

19-9468

CAPLA Addition and Renovation

CAPLA has recently completed the pre-design Programming that is aligned with the College's overall Strategic Plan, with the goal being to improve space utilization and provide academic facilities that will enhance learning and support the growth of academic programs. CAPLA would now like a review of the overall Conceptual Master Plan of the entire Program. Thereafter developing a full Conceptual Design of the entire existing CAPLA West building and a potential new CAPLA South building. The first phase of the project in CAPLA West, will then be identified. Future phases will be contingent on the availability of funds.

Conceptual overall master planning is ongoing. Phase 1 (CAPLA West) conceptual design is ongoing.

Current Budget
$450,000
Projected Ultimate Budget
$2,450,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Richard + Bauer
Construction Schedule
May 2020 - September 2020
Contractor
None

18-9407

Castro House Renovations

Conversion, restoration and renovation of the historic Castro House from a residential use to The Raul H. & Patricia M. Castro Center for Border Studies and Outreach. Renovations to include a community education center and library that will engage the community and promote collaboration and sharing of resources. Accessibility upgrades are planned for the site and within the building.

This project is in the Construction Documents and construction cost estimating phase.

Current Budget
$350,000
Projected Ultimate Budget
$1,250,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
B W S -Burns Wald-Hopkins Shambach Architects
Construction Schedule
April 2020 - October 2020
Contractor
Lloyd Construction Co Inc

19-9473

Chemistry Building Renovations

Renovate the centrally located, historic Old Chemistry Building into an innovative teaching hub, that supports evidence-based teaching strategies (collaboration, inclusive practices, and active learning). The project is Initiative 1.3B1 of the UA Strategic Plan. Deferred maintenance, life safety, accessibility, code upgrades, and sustainability will also be addressed.

Pre-planning is underway and the design phase is ready to begin.

Current Budget
$7,225,000
Projected Ultimate Budget
$42,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Shepley Bulfinch
Construction Schedule
January 2021 - May 2022
Contractor
Sundt Construction

18-9390

Cole and Jeannie Davis Sports Center

The new building provides a safe, all-weather football practice facility and a multi-use facility for multiple sports, as well as an additional game-day venue.

Current Budget
$16,300,000
Projected Ultimate Budget
$16,300,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
BWS & HOK
Construction Schedule
April 2018 - February 2019
Contractor
M. A. Mortenson Company

17-9362

College of Pharmacy Skaggs Building Addition and Renovation

This project will provide the College of Pharmacy with both new and renovated state-of-the-art research lab facilities to ensure its growth and capacity to adapt to the dynamic and changing fields in pharmaceutical sciences. The College of Pharmacy intends to continue its innovation and excellence in research, practice and education and make a substantial impact on improving the health of people of Arizona and around the world. The new two-story addition will house biology and chemistry research labs. A separate smaller addition will display items from the Pharmacy Museum collection. Some existing building areas will be renovated, including research labs and administrative offices.

Construction is in full swing. The building envelope is progressing quickly. The interiors will be fully weather protected soon. And the museum addition is catching up and will complete with the rest of the project in November / December.

Current Budget
$26,000,000
Projected Ultimate Budget
$26,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
G L H N Architects And Engineers
Construction Schedule
September 2018 - November 2019
Contractor
DPR Construction

19-9488

College of Pharmacy Skaggs Building Tenant Improvement

With this tenant improvement project many existing office spaces and laboratories in the Skaggs Building will receive a refurbishment to coincide with and complement the on-going College of Pharmacy Addition and Renovation Project. The improvements to the existing spaces will include painting, flooring, and lighting.

The project is underway and is scheduled to complete in November /December 2019.

Current Budget
$272,000
Projected Ultimate Budget
$272,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
GLHN Architects & Engineers
Construction Schedule
TBD - TBD
Contractor
DPR Construction

16-9334

COM-Phoenix (Administration) Bldg 3002, Eller Administrative Suite Remodel

Remodel of 2nd floor east half of Building 1 on the Phoenix Biomedical Campus to accommodate new administrative offices for Eller Executive and Evening MBA programs.

Current Budget
$615,292
Projected Ultimate Budget
$615,292
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
SmithGroupJJR
Construction Schedule
September 2016 - December 2016
Contractor
DL Withers

55-2946

DAS Mckale Memorial Center

This project involved the installation of a distributed antenna system (DAS) within McKale Memorial Center to improve cell service during events.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

19-9461

Education Building, 2nd and 3rd Floor Renovations

The College of Education is implementing their Strategic Plan that will relocate and create a Student Services Hub which in effect, will be the face of the College. In addition, the College will be increasing efficiencies in their operations by improving space utilization by relocating and reconfiguring some of their academic programs.

Project is in UA Administrative review.

Current Budget
TBD
Projected Ultimate Budget
$2,500,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
May 2020 - September 2020
Contractor
None

18-9423

ENR II Rooftop Solar Installation

Installation of Photovoltaic panels and roof top gardens.

Roof is being prepared for column stub ups.

Current Budget
$510,000
Projected Ultimate Budget
$510,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
G L H N Architects And Engineers
Construction Schedule
October 2019 - February 2020
Contractor
Core Construction

55-8004

Facilities Management, Building 65 Plan Review and Inspection

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

18-9384

Grand Challenges Research Building

The Grand Challenges research building will be an interdisciplinary facility providing new laboratory space for growth of research programs. The building is envisioned to be a six floor building located on the main campus.

This project is in the programming/concept design phase.

Current Budget
$7,800,000
Projected Ultimate Budget
$99,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
October 2020 - December 2022
Contractor
None

13-9182

Health Science Education Building, Finish Shell Space

This Tenant Improvement project in the Health Sciences Education Building will include a regional Simulation Center, completion of a Lecture Hall, administrative space, a Presidential Suite and the possible inclusion of classroom/Learning Studio space. Projects 13-9182 (HSEB, Finish Shell Space), 13-9206 (HSEB Finish Shell Space UA), and 13-9207 (HSEB Finish Shell Space NAU) will be covered under this description.

Current Budget
TBD
Projected Ultimate Budget
$17,900,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
January 2014 - July 2014
Contractor
None

09-8900

Health Sciences Education Building

The building on the Phoenix Biomedical Campus (PBC), 435 N. 5th Street, Phoenix 85004, includes flexible classrooms and state-of-the-art educational facilities, such as, simulation laboratories, gross anatomy facilities, preclinical training, learning resource center, student services and faculty office administrative space.

The HSEB creates an iconic identity for the University of Arizona School of Medicine on the Phoenix Biomedical Campus and responds to its urban locale and desert environment. The Arizona desert climate and need for reduced energy consumption informed much of the design, from the way the building is sited at its location to the type of fenestration and the innovative cooling methods used. Inspired by the iconic canyon formations found throughout Arizona, the façade reinterprets stratified earth layers revealed over time as a copper sunscreen protecting the exterior building enclosure from direct solar exposure. Akin to the natural forces that shape the Earth’s geology, the copper skin is fissured, formed, bent, pressed, and perforated, creating beauty from a functional building need. The architectural design promotes physical connectivity to the downtown Phoenix community with indoor and outdoor spaces that encourage interaction.

Current Budget
$135,998,801
Projected Ultimate Budget
$135,998,801
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
July 2010 - July 2012
Contractor
D P R / Sundt (A Joint Venture)

13-9193

Health Sciences Innovation Building

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

The building interior was deliberately designed without columns to provide more flexibility of space in the future. Approximately 1,000+ people can be accommodated in the Forum for special events. Spaces known as “flipped classrooms” can accommodate up to 150 students for interactive learning. Terra cotta, a material that emulates brick, will create natural shade on the east façade where glass walls have been constructed.

Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
June 2016 - May 2019
Contractor
Kitchell

18-9388

Hillenbrand Aquatic Center Improvements

The Hillenbrand Aquatic Center Swimming Pool, Pump/Filtration Room and Chemical Room underwent a life-cycle replacement. The pools structural integrity was severely degraded and the mechanical filtration system was corroded and unsafe. The new pool is not only significantly longer (70m) but has state-of-the-art technology for practicing and for competition. The pool also accommodates multiple bulkheads. The Old Dive Pool was demolished to create the space needed for the longer pool.

Current Budget
$13,250,000
Projected Ultimate Budget
$13,250,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Architekton
Construction Schedule
April 2018 - December 2018
Contractor
CORE Construction, Inc.

20-9504

Hillenbrand Softball Stadium Remodel

Current Budget
$20,000
Projected Ultimate Budget
$150,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

17-9382

Hillenbrand Softball Stadium Renovations

The existing softball stadium was renovated to improve the experience for the dedicated fan base by adding new sun shading , loge and standing areas, restrooms and concessions. The press box was renovated, the dugouts were upgraded, and the backstop netting system was replaced.

Current Budget
$8,000,000
Projected Ultimate Budget
$8,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Swaim Associates
Construction Schedule
June 2018 - February 2019
Contractor
Concord General Contracting

14-9227

HSEB - NAU Occupational Therapy Area Improvements

Project consists of the remodel of the existing occupational therapy rooms in the Health Science Education Building to accommodate new equipment that is being purchased by Northern Arizona University.

Current Budget
$170,716
Projected Ultimate Budget
$170,716
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2014 - July 2014
Contractor
None

19-9466

HSIB, Levels 1, 2 and 6 Remodeling

Remodel portions of Levels 2 and 6 in the Health Sciences Innovation Building to accommodate new programs.

Current Budget
$1,300,000
Projected Ultimate Budget
$1,300,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
September 2019 - October 2019
Contractor
D P R Construction, Inc., A General Partnership

18-9401

Main Library, 4th and 5th Level Relocations

Renovation to portions of the 1st & 4th Level pods of the Main Library to accommodate reorganization of library staff. Phase 1 renovations include areas on the 1st & 4th Level of Main Library and a portion of the 1st Level of Science Engineering Library. 5th Level Renovations and upgrades to toilet rooms on 3rd, 4th & 5th Level of the Main Library are anticipated for Phase 2.

Construction of the first two phases are complete. Phase 3 is in design and the associated work will occur Summer 2020.

Current Budget
$2,950,000
Projected Ultimate Budget
$2,950,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Gould Evans Architects
Construction Schedule
December 2018 - April 2019
Contractor
Core Construction

20-9505

Maricopa County Cooperative Extension, Demonstration Kitchen Remodeling

Remodel of the existing classroom and kitchen area at the Maricopa County Cooperative Extension Facility at 4341 E. Broadway Road.

Design scope is being finalized with user group.

Current Budget
$30,000
Projected Ultimate Budget
$183,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
January 2020 - February 2020
Contractor
None

18-9404

Marvel Labs Rm 506,514,550,554 Renovation

Renovate 4 lab modules to be suitable for organic Chemistry in support a relocation from old chemistry

Current Budget
$1,000,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Sears Gerbo Architecture
Construction Schedule
October 2018 - February 2019
Contractor
R. W. Burkel

18-9385

McKale Memorial Center, Locker Room Suite 170 Remodel

In order to improve student athlete support areas, Intercollegiate Athletics (ICA) added 4 new locker rooms and remodeled 2 existing locker rooms to include lounge/team areas, kitchenette, etc.

Current Budget
$1,900,000
Projected Ultimate Budget
$1,900,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Swaim Associates, Ltd
Construction Schedule
April 2018 - August 2018
Contractor
Concord General Contracting

19-9433

Mirror Lab Storage Rack

Provide a racking system to facilitate the safe and secure storage of three 8.4 meter mirrors.

Current Budget
$41,125
Projected Ultimate Budget
$41,125
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
M3 Engineering
Construction Schedule
TBD - TBD
Contractor
None

19-9487

Multiple Parking Garage Maintenance and Repairs 2019

In 2019, a "Conditions Evaluation and Preventative Maintenance Report" was commissioned for all of the parking garages on Campus. This project addresses all of the needs that were identified in that report to repair and maintain these garages. The plans and specifications for the work were done in time for the actual repairs and maintenance to start in the summer of 2019. This work assures that the garages are maintained in good condition and remain serviceable for the foreseeable future. The list of Garages included in this project are: Sixth Street, Tyndall Avenue, Main Gate, Park Avenue, Highland Avenue, Second Street, Cherry Avenue, and the Health Sciences Garage.

Current Budget
$320,000
Projected Ultimate Budget
$320,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
July 2019 - December 2019
Contractor
None

16-9323

Multiple Parking Garage Maintenance Repairs 2017

In 2013, a "Conditions Evaluation and Preventative Maintenance Report" was issued for all of the parking garages on Campus including the Highland Avenue, Park Avenue, Tyndall Avenue, Sixth Street, and Main Gate Garages. This project will address all of the needs that were identified in that report to repair and maintain these five garages in 2017. The actual repairs and maintenance will be done in the summer of 2017. This work will assure that these five garages are maintained in good condition and remain serviceable for the foreseeable future.

Current Budget
$700,000
Projected Ultimate Budget
$700,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Desman Associates
Construction Schedule
May 2017 - October 2007
Contractor
Core Construction

12-9135

North Campus Infrastructure

North Campus Infrastructure was a multi-stage, multi-element project which expanded the University's existing infrastructure including, but not limited to mechanical; electrical; telecommunications utility distribution systems; central plant heating, chilled water and potable water production; sewer and surface drainage to support the new Bioscience Research Lab Building, the proposed Applied Sciences building and future campus growth.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2015 - May 2016
Contractor
Sundt Construction Inc

17-9349

Oro Valley Veterinary Medicine Facility

The Oro Valley Veterinary Medicine Facility will be the administrative and pre-clinical training headquarters for the University of Arizona's College of Veterinary Medicine program. This project will provide the renovations and equipment to facilitate the necessary programmatic areas to support student teaching, learning and hands-on experience.

Current Budget
$8,000,000
Projected Ultimate Budget
$8,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
December 2018 - July 2019
Contractor
Lloyd Construction Co Inc

17-9364

Parking Lot Improvements 2017

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8178 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Current Budget
$676,000
Projected Ultimate Budget
$676,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Eagle Rock and DFDG/GLHN
Construction Schedule
May 2017 - December 2017
Contractor
Eagle Rock Excavating and McCarthy

18-9410

Parking Lot Improvements 2018

Pave and stripe Lots 7102, 5083, 5072 and 6072. Seal coat and stripe Lots 7103, 2029, 7156 and 7228. Landscape Lots 7102, 7103 and 2030. Add motorcycle parking to Lot 5084.

Current Budget
$1,000,000
Projected Ultimate Budget
$1,030,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
PD&C
Construction Schedule
June 2018 - October 2019
Contractor
Ashton Company Inc The

18-9425

PBC ABC1 4th Floor Lab Remodel

Remodel of an existing chemical fume hood area into a tissue culture room on the 4th floor of the Arizona Biomedical Collaborative Building 1. Work involves removing existing chemical fume hoods, and installing biosafety cabinets in its place. Work also involves relocating doors, repairing finishes, and adjusting air balance.

Current Budget
$113,000
Projected Ultimate Budget
$113,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
SmithGroup
Construction Schedule
TBD - TBD
Contractor
McCarthy Building Companies

18-9396

PBC, NW Corner of 7th St and Pierce St, Development, Demolition & Site Prep

Feasibility study for the single family houses, duplex and the commercial property on the Phoenix Biomedical Campus.

Demolition for existing commercial building, and the two single family houses has been completed. Study is ongoing for duplex property.

Current Budget
$275,000
Projected Ultimate Budget
$275,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

19-9449

Phoenix BSPB 3rd & 4th Floor Finish Shell Space

The fit out of the 3rd and 4th floor shell space of Biomedical Sciences Partnership Building into additional wet lab space on the Phoenix Biomedical Campus.

50% Construction Documents are on target to be completed on November 1, 2019. Pricing exercise is underway.

Current Budget
$34,000,000
Projected Ultimate Budget
$34,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
CO Architects
Construction Schedule
January 2020 - January 2021
Contractor
D P R / Sundt (A Joint Venture)

18-9391

Pima County Court House, Gem and Mineral Museum Relocation

The College of Science is looking to relocate the Gem and Mineral Museum to the Old Pima County Courthouse. The Lower Level 9,200sf will be a Research Lab, Community and Storage. The Upper Level 1 (Main Level) 11,700sf- will be the Gem and Mineral Museum gallery of Exhibits.

Construction is ongoing.

Current Budget
$100,000
Projected Ultimate Budget
$100,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Pima County (Poster Frost Mirto)
Construction Schedule
September 2019 - October 2020
Contractor
Pima County (Design&Production, Inc.)

19-9477

Poetry Center Reading Area 101 Remodel

In order to address continued program growth as well as review existing inefficiencies in space usage, the Poetry Center intends to remodel Reading Area 101 and Display 101B for optimal exhibit space arrangement and seating utilization.

Construction Documentation is ongoing.

Current Budget
$50,000
Projected Ultimate Budget
$255,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Line and Space, LLC
Construction Schedule
May 2020 - July 2020
Contractor
Kappcon General Contracting

18-9408

Roy Place Renovations

Construction of toilet rooms, along with other building system upgrades and building modernization for tenant improvements on the 1st and 2nd floors. Renovations to include the main public areas and tenant fit-out areas on the 1st floor; business startup / incubator space, kitchenette, office areas, and conference rooms on the 2nd floor.

Demolition is completed and renovation for phase 1 is underway. Work on essential building water, sewer, electrical roofing and HVAC systems is in progress.

Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Merry Carnell Schlecht Inc.
Construction Schedule
July 2019 - February 2020
Contractor
Barker Contracting, Inc.

08-8847

Solar/Sustainable Initiatives

A solar/sustainable initiative is underway that is being facilitated through the University's partnership with AMERESCO to advance solar technology awareness on campus and throughout the community. Through this initiative solar installations are planned for Second Street Garage, Student Recreation Center, McClelland Hall, McClelland Park, Hillenbrand Aquatic Center, Red Rock Ag Center, Campus Ag Center, Controlled Environmental Ag Center, West Campus Ag Center, Ville Del Puente Res Hall, and Posada San Pedro Res Hall.

Current Budget
$460,500
Projected Ultimate Budget
$460,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
AMERESCO
Construction Schedule
July 2009 - July 2012
Contractor
AMERESCO

19-9450

South Stadium Rowhouses

This College of Architecture, Planning & Landscape Architecture (CAPLA) student design-build project will provide new faculty/staff temporary housing. Five proposed row houses will be located along Seventh Street, adjacent to the South Stadium Parking Garage. The row houses are planned to be constructed one at a time, phased over seven years.

Construction of the first rowhouse unit is underway, with the building shell having been completed by the Spring 2019 semester class. The Fall 2019 semester class is completing the interior work. Site prep is underway for the second rowhouse.

Current Budget
$405,000
Projected Ultimate Budget
$405,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
CAPLA
Construction Schedule
February 2019 - May 2025
Contractor
CAPLA

17-9376

Southwest Center, Building 375, 375A & 375B Repairs

The College of Social and Behavioral Sciences intends to conduct roofing repairs and remedial work on these three buildings which are part of their Southwest Center program.

Current Budget
$554,500
Projected Ultimate Budget
$554,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2017 - July 2018
Contractor
Lloyd Construction Co Inc

16-9321

Student Recreation Center, Locker Room Remodel

This is a comprehensive locker room remodel to achieve greater inclusivity for all Recreation Center patrons, as well as update the 25 year old facilities with more contemporary design features and finishes.

Current Budget
$4,945,000
Projected Ultimate Budget
$4,945,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Breckenridge Group
Construction Schedule
March 2017 - August 2017
Contractor
Lloyd Construction

17-9381

Student Success District

The new Student Success District will integrate and revitalize student services in four adjacent central campus buildings: Main Library, Weaver Science-Engineering Library, Bear Down Gym, and a new Student Services Building. The project will also include site development improvements.

Construction is underway on the Main Library, Weaver Science-Engineering Library and the Student Success Building. Design is in process for Bear Down Gym and remaining site development.

Current Budget
$81,000,000
Projected Ultimate Budget
$81,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Poster Frost Mirto
Construction Schedule
January 2019 - October 2021
Contractor
Sundt

20-9511

SUMC, Room 205 Patio Renovation

Arizona Student Unions would like to improve the use of Pangea Restaurant patio space by providing an enclosure with soft seating and re-imagining the outdoor retail experience.

Project is in UA Administrative Review.

Current Budget
TBD
Projected Ultimate Budget
$300,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
May 2020 - August 2020
Contractor
None

18-9399

SUMC, Room 226A Starbucks Remodel

In order to improve student food service and retail experience, UA Bookstores reconfigured and expanded the existing Starbucks in the Memorial Student Union.

Current Budget
$440,000
Projected Ultimate Budget
$440,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Merry Carnell Schlecht (MCS)
Construction Schedule
July 2018 - July 2018
Contractor
CORE Construction, Inc.

10-9001

UA Cancer Center-Phoenix - Phase I

This new facility provides the highest quality cancer research and care with an evidence-based, multi-disciplinary model, along with the modern technologies, and a compassionate patient-centered approach. The building is located at 625 N. 6th St, on the northwest corner of Fillmore and Seventh Streets on the downtown Phoenix Biomedical Campus.

Current Budget
$100,000,000
Projected Ultimate Budget
$100,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsel Frasca
Construction Schedule
January 2013 - May 2015
Contractor
Hensel Phelps Construction Co.

19-9463

UA Global Center, Park Student Union Renovations

Renovations to former Park Student Union (PSU) will accommodate relocation and consolidation of the UA Global's functions from elsewhere on campus. The resulting Global Center will serve as a hub for international activities on Campus. The project is Initiative 4.2C4 of the UA Strategic Plan.

Phase 1 of the Global Center renovation work is substantially complete and occupied. Phase 1 also included renovations in USB, Haury and 1221 E. Helen St. to accommodate relocation of KAMP Radio, an Anthropology lab and Festival of Books. The RFQ process to select a Design-Build team for Phase 2 is in progress.

Current Budget
$8,500,000
Projected Ultimate Budget
$8,500,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
GLHN Architects & Engineers
Construction Schedule
May 2019 - July 2021
Contractor
WE O'Neil Construction

18-9395

UA Honors Village

The University of Arizona has entered into a Public Private Partnership agreement with American Campus Communities to develop, design and construct the UA Honors Village, a multi-building complex consisting of a 1056 bed Honors Dorm, that also includes academic space and food services, a Recreation Center and a 4 story, 370 space Parking Structure.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
STG Architects
Construction Schedule
November 2017 - July 2019
Contractor
Okland Construction

15-9286

UAHS BSPB 10th Floor Finish Shell Space

Fit out of Level 10 in BSPB for new administrative offices for the College of Medicine Phoenix.

Current Budget
$8,550,000
Projected Ultimate Budget
$8,550,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
June 2018 - December 2018
Contractor
D P R / Sundt (A Joint Venture)

17-9363

UAHS Building 201 Renovations

As part of the University of Arizona/Banner Health initiative, a number of UAHS departments need to be relocated. To facilitate this phased relocation effort, existing space on multiple levels in Building 201 was renovated to provide the administrative and ancillary support associated with UAHS departments.

Current Budget
$14,500,000
Projected Ultimate Budget
$14,500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN Architects & Engineers
Construction Schedule
January 2018 - April 2018
Contractor
Lloyd Construction Co Inc

16-9313

UITS Infrastructure Upgrade

This project upgraded the existing IT Data Network Hubs for a systems upgrade to 100GB network.

Current Budget
$360,000
Projected Ultimate Budget
$360,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design and Construction
Construction Schedule
March 2016 - May 2016
Contractor
Sturgeon ELectric

19-9475

Yavapai Building Renewal

This project will upgrade/replace the existing building’s Mechanical, Plumbing and Electrical systems. In addition, overall building accessibility will be improved via installation of an elevator and the creation of accessible rooms.

Demolition is underway. Long lead items have been ordered. Construction documents are complete and will be issued for comments and GMP preparation.

Current Budget
$9,500,000
Projected Ultimate Budget
$9,500,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
GLHN
Construction Schedule
September 2019 - July 2020
Contractor
Lloyd Construction Co Inc