22-9607

AME Hypersonic Wind Tunnel Complex Upgrades

Augment the compressed air system to improve runtime of the AME Hypersonic wind tunnel

Design for tank installation and power feeds are underway. Compressor yard design is starting. submittal review of pre-purchased items is ongoing.

Current Budget
$3,730,000
Projected Ultimate Budget
$3,730,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
GLHN
Construction Schedule
September 2023 - December 2023
Contractor
None

19-9472

Andrew Weil Center for Integrative Medicine

This project will develop a new facility for the Andrew Weil Center for Integrative Medicine (AWCIM) to centralize their operations in a physical building and landscape environment that supports their philosophy of healthy work environments.

Masonry walls (CMU) is nearing completion. Mechanical, electrical, plumbing rough-in is in progress. The Main Office Building structural steel framing continues and will begin steel stair construction and Level 2 & 3 floor decking. MPR roof installation, interior shaft wall framing, interior overhead mechanical and electrical systems, starting with main piping for fire sprinkler and large duct systems is underway.

Current Budget
$23,000,000
Projected Ultimate Budget
$23,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Line and Space, LLC
Construction Schedule
May 2022 - November 2023
Contractor
DPR Construction

18-9386

Applied Research Building

The new Applied Research Building (ARB) is a very specialized, one of a kind research facility designed specifically for UA applied research programs. This three-story building has a variety of programmed spaces, including high bay payload assembly areas, a large scale thermal vacuum chamber, unique research / customized laboratories, clean rooms, faculty offices, collaboration spaces, and conference rooms. The ARB will be located at the southeast corner of Helen Street and the Highland Corridor. The Highland Corridor will be improved and realigned as part of this project to provide safer pedestrian and bicycle crossings at Helen Street.

Building is substantially complete. Punch list completion and additional scope items in progress.

Current Budget
$85,000,000
Projected Ultimate Budget
$85,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
SmithGroup
Construction Schedule
June 2021 - March 2023
Contractor
McCarthy Building Companies

22-9576

Arizona Public Media New Facility

Arizona Public Media (AZPM) is an editorially independent, member supported, not-for-profit public media organization provided by the University of Arizona as an educational and informational community service. AZPM exemplifies the goals and objectives of public media and furthers the land-grant mission of the University, serving all or parts of eleven Arizona counties with three public television program services, three public radio services, and a variety of online services at azpm.org. In addition to delivering programs from PBS, NPR, and the BBC, among others, AZPM produces award-winning original newscasts, public affairs programs, documentaries, and community engagement events for and about the people of Southern Arizona. A new, modern facility for Arizona Public Media will better serve ever-changing community needs and interests, support the education and training of University of Arizona students, improve visibility and community access, and model the transparency aspect of journalism. The new 50,000 sf facility will be designed specifically to meet current and future technical and broadcast requirements, including the replacement of much of AZPM’s aging broadcast production infrastructure as we transition to 4K production in preparation for the conversion to a new television broadcast standard (NextGen TV).

Project is in construction document phase.

Current Budget
$5,000,000
Projected Ultimate Budget
$45,000,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
SmithGroup + Swaim
Construction Schedule
July 2023 - February 2025
Contractor
DPR Construction, Inc., A General Partnership

22-9587

Arizona Stadium, Synthetic Turf Resurfacing

Resurfacing of the synthetic turf surface and surrounding running track apron at Arizona Stadium to counter the effects of aging and wear and to improve stadium aesthetics and the safety of student athletes.

Current Budget
$1,400,000
Projected Ultimate Budget
$1,400,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Lloyd Sports + Engineering
Construction Schedule
May 2022 - July 2022
Contractor
KappCon

22-9614

Bear Down Field Turf Replacement

This project will resurface the 69, 616 square foot Bear Down field with a new layer of 2.5" artificial turf. The existing field will have the perimeter trimmed back and be re-leveled with sand. New fabric with markings matching the existing markings will then be installed over the old fabric.

Current Budget
$450,000
Projected Ultimate Budget
$450,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
December 2022 - January 2023
Contractor
Kappcon Inc

12-9134

Bioscience Research Laboratories

The BSRL provides research facilities to support interdisciplinary research in many health science disciplines. This new facility encourages collaborative translational research that will advance understanding of the molecular basis of human health, aging and disease.

Build-out of basement shell space is in progress. Current phase of work will complete pending life safety and fire alarm inspections. Areaway lid has been reinstalled. Side walk to be replaced in February. Magnetic Shielding design and installation is deferred to next project phase, pending purchase of MRI equipment.

Current Budget
$107,500,000
Projected Ultimate Budget
$107,500,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Zimmer Gunsul Frasca Architects, LLP
Construction Schedule
December 2015 - December 2022
Contractor
D P R Construction Inc

22-9604

Building 73, Room 120 and 215 Electrical Upgrade

This project is to remove underrated panels. The project also includes reworking the normal and emergency feeders to the distribution units in Rm 215 and Rm 214.

JOC Contractor has been Selected.

Current Budget
$100,000
Projected Ultimate Budget
$100,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
UA PDC
Construction Schedule
TBD - TBD
Contractor
Gilbert Electric

23-9652

Campus Agricultural Center National Register District Nomination

The University of Arizona seeks to nominate a portion of the Campus Agricultural Center on Campbell Avenue as a National Register Historic District due to its historical significance in the area of education and agriculture related to the College of Agriculture. The district will include representative open space, buildings and structures dating from 1909-1950. The DP will complete a National Register Nomination Form for submission to the State Historic Preservation Office and assist the University in navigating the nomination process.

On-site field work and historical research is underway.

Current Budget
$50,000
Projected Ultimate Budget
$50,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Westland Resources Inc
Construction Schedule
TBD - TBD
Contractor
None

15-9248

Campus Research Infrastructure

Campus Infrastructure is a multi-phase, multi-element project which will supplement existing infrastructure to support new research buildings being constructed and future growth. The installation of large storage tanks beneath the east Main Mall will mitigate surface water run-off from large rainstorms on Cherry Ave. and reduce the risk of flooding of University buildings and impacts to 6th Street and neighborhoods to the south. During a rainstorm, catch basins installed in University Blvd and Cherry Ave will intercept and channel storm water to a series of interconnected, 10 feet diameter, 20 feet long underground tanks installed under the east Mall where it will gradually dissipate into the ground. Upon completion, the system will accommodate a I hour rainfall event of up to 2.3 inches.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
August 2021 - October 2022
Contractor
Sundt Construction Inc

19-9468

CAPLA Addition and Renovation

The College of Architecture, Planning & Landscape Architecture’s (CAPLA) Strategic Plan includes goals to enhance learning and support increased student enrollment by improving and better utilizing their facilities. This project prioritizes natural ventilation and additional student studio spaces with a more significant energy efficient exterior window wall system and whole building natural ventilation in the West Building.

Current Budget
$9,802,000
Projected Ultimate Budget
$9,802,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Richard Kennedy Architects
Construction Schedule
March 2022 - January 2023
Contractor
CORE Construction, Inc.

21-9542

Center for Creative Photography Entry Renovation

Exterior renovations to the main entry will improve visibility, wayfinding and integration into the Arts Master Plan

Current Budget
$140,000
Projected Ultimate Budget
$140,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
DLR
Construction Schedule
August 2021 - February 2022
Contractor
DPR

19-9458

Center for Creative Photography, 2019 Remodeling and Renovations

Renovate portion of first floor to create a multimedia gallery, renovate offices, and improvements to the environmental control system for Archives.

Cold Storage walls and Ceilings complete. Waiting for delivery and installation of enclosure refrigeration equipment.

Current Budget
$3,447,200
Projected Ultimate Budget
$3,447,200
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Sears Gerbo Architecture
Construction Schedule
January 2020 - June 2023
Contractor
D P R Construction, Inc., A General Partnership

19-9473

Chemistry Building Renovations

This Strategic Plan initiative will renovate and repurpose the historic Chemistry Building, centrally located on the Mall, into an innovative teaching hub. Evidence-based teaching strategies (collaboration, inclusive practices, and active learning) result in increased student learning, engagement, and development of workplace-relevant skills. Deferred maintenance, life safety, accessibility, code upgrades, and sustainability will also be addressed.

Remaining work includes IT, AV, and Security installation, finalizing finishes and FFE install, and punch list items. Occupation began in Feb. Full classroom functionality expected by April 15th. Elevator to be installed over summer of '23.

Current Budget
$42,000,000
Projected Ultimate Budget
$42,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Shepley Bulfinch
Construction Schedule
May 2021 - December 2022
Contractor
Sundt Construction

20-9527

College of Fine Arts Master Plan Implementation

Arizona Arts has been given a major role in the University's Strategic Plan to integrate the arts into all aspects of the University and establish UArizona as an arts destination and increase both local and national awareness. To realize this strategic vision, a master plan has recently been completed that outlines series of projects implemented through a multi-year, multi-phased manner as funding becomes available. The initial phase will consist of renovations of the Art Building.

Current Budget
$6,001,573
Projected Ultimate Budget
$6,030,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
RSP Architects
Construction Schedule
July 2021 - August 2022
Contractor
CORE Construction

21-9557

College of Pharmacy Skaggs Building Lab Renovation

Renovation to provide 3 new labs in the existing building.

Current Budget
$1,500,000
Projected Ultimate Budget
$1,500,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
July 2021 - November 2021
Contractor
DPR

22-9595

ECE Micro-Nano Center Renovation

Renovate existing lab 316 infrastructure to support future programs.

Generator and Gas monitoring package is complete. Additional funding is in process to allow construction to begin.

Current Budget
$1,900,000
Projected Ultimate Budget
$1,900,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Sears Gerbo Architecture
Construction Schedule
April 2023 - July 2023
Contractor
RW Burkel

19-9461

Education Building, 2nd and 3rd Floor Renovations

The College of Education is implementing their Strategic Plan that will relocate Student Services to just inside the main entry of the Education Building.

Current Budget
$1,500,000
Projected Ultimate Budget
$1,500,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Line and Space, LLC
Construction Schedule
August 2021 - December 2021
Contractor
Kappcon

22-9605

Forbes Building, Room 206 Renovation

Conversion of a 600 Sq.Ft. classroom, conference room and portions of the reception area to house (5) new offices to serve life management counselors and multi-purpose student collaboration area as part of the student support team.

Mobilization and demolition to commence at end of February with new construction to immediately follow. Substantial Completion is targeted for mid-July for occupancy on August 1, 2023

Current Budget
$1,200,000
Projected Ultimate Budget
$1,200,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
February 2023 - June 2023
Contractor
Lloyd Construction

22-9590

GCRB, Level 6 Tenant Improvements

Tenant improvement for Grand Challenges Research Building sixth floor shell space.

Project is in construction phase .

Current Budget
$7,000,000
Projected Ultimate Budget
$7,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
September 2022 - February 2024
Contractor
Kitchell Contractors

18-9384

Grand Challenges Research Building

GCRB is a new research facility that will leverage the University of Arizona's core strengths to address the grand challenges identified in Pillar 2 of the University's strategic plan. GCRB will be an interdisciplinary facility designed to foster conversations among sciences and programs. The 7-story building will be located on Cherry Avenue as part of the Wyant College of Optical Sciences complex. The new building will be south of Meynell West, and across the street from the Main Library. GCRB will support research laboratories for expansion of the Optical Sciences under the Office of the Provost to continue advancing the University's international reputation in this field, as well as new sponsored projects for the Office of Research Innovation and Impact.

Project is in construction phase. The structure is complete. The work on the building facade is also nearing completion. The interior construction has progressed from the basement through the 6 floor with framing, drywall, and MEP systems. The site utilities are getting tied-in and commissioned. And building finishes are schedule to schedule to begin in the coming weeks.

Current Budget
$99,000,000
Projected Ultimate Budget
$99,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
ZGF Architects/BWS Architects
Construction Schedule
July 2021 - January 2024
Contractor
Kitchell Contractors, Inc. of Arizona

22-9609

HSEB, Pharmacy Teaching Lab Renovation

Renovation of existing classroom space in HSEB to accommodate a new Pharmacy Teaching Lab.

Current Budget
$299,000
Projected Ultimate Budget
$299,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
McCarthy Building Companies
Construction Schedule
September 2022 - November 2022
Contractor
McCarthy Building Companies

19-9466

HSIB, Levels 1, 2 and 6 Remodeling

Remodel portion of Level 1 in the Health Sciences Innovation Building to accommodate food service.

Exterior infrastructure, Basement and Level 1 Mechanical, Electrical, Plumbing work is in progress. Level 1 interior wall and flooring finishes are nearing completion. Architectural Millwork and kitchen equipment install is underway.

Current Budget
$7,800,000
Projected Ultimate Budget
$7,800,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
CO Architects
Construction Schedule
September 2019 - March 2023
Contractor
Kitchell Contractors

22-9563

ICA Hi Corbett 2021 Renovations

Renovation and modernization of the baseball team facility to include training rooms, lounge / eating / kitchen facilities, and team meeting room to meet short term needs. Along with immediate needs, a master plan will be developed for multi-phase long-term goals to improve other areas of the facility for fan engagement and recruitment of talent.

Owner occupation expected on 24 Feb 23. Punchlist and new scope work will continue through May.

Current Budget
$2,750,000
Projected Ultimate Budget
$2,750,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
BWS Architects
Construction Schedule
August 2022 - February 2023
Contractor
Concord General Contracting

22-9596

LSFF, Player's Locker Rooms Remodel

Interior finish upgrades of the Lowell Stevens Football Facility to player's locker rooms and support spaces.

Current Budget
$1,400,000
Projected Ultimate Budget
$1,950,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
May 2022 - July 2022
Contractor
None

22-9593

Manuel Pacheco Integrated Learning Center Room 136 Renovations

The Department of Digital Learning and the Office of Instruction and Assessment will be collaborating on online teaching and learning initiatives as they come together to form a Teaching and Learning Center in a renovated space in ILC.

Construction Documents are in progress.

Current Budget
$700,000
Projected Ultimate Budget
$700,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
April 2023 - July 2023
Contractor
Kappcon

20-9505

Maricopa County Cooperative Extension, Demonstration Kitchen Remodeling

Remodel of the existing classroom and kitchen area at the Maricopa County Cooperative Extension Facility at 4341 E. Broadway Road.

Construction documents are completed and are being submitted to the local authority have jurisdiction for permits.

Current Budget
$407,000
Projected Ultimate Budget
$407,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
GLHN Architects And Engineers
Construction Schedule
June 2020 - October 2022
Contractor
McCarthy Building Companies

21-9548

Marroney Theatre Renovations & Addition

Renovations to upgrade the educational aspects and enhance the patron experience of the theatre.

Selective demolition of the seating and ceiling in the theatre, and related abatement is completed. Demolition of the ticket booth and lobby is completed. The canopy over the main entrance has been removed, integrated artwork stored, and ornamental columns relocated in preparation for modifying the spandrel beam to accommodate the new glazed curtain wall. Renovation is progressing in the front of house, restrooms, beam port, and entrance plaza under GMP 1. GMP 2 plans have been issued and pricing has begun for replacement of the house seating and theatre equipment.

Current Budget
$8,500,000
Projected Ultimate Budget
$8,500,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
RSP Architects
Construction Schedule
November 2022 - August 2023
Contractor
Core Construction

23-9628

McClelland Park Renovation, Retail Learning Lab

The renovation project will include a Concepts and Collaboration Learning Space, an application based Retail Technology Virtual Reality Learning Lab, and an implementation area for retail sales in the Lobby.

Conceptual Design is substantially complete.

Current Budget
$250,000
Projected Ultimate Budget
$250,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
DLR
Construction Schedule
June 2023 - September 2023
Contractor
WE ONeil Construction Company Inc

23-9629

Multiple Pkg Garage Maint, Repairs & Parking Lot/Bike Path Imp FY23

Maintenance, repairs, and Improvements to ten parking structures, six parking lots and one bike path.

Science Concourse bike path and ramp at Park are completed. Parking lots 3113, 1016.2, 4059, 2235, 7121 are paved. Garages repairs at Health Sciences, Highland, Honors, Park Ave., Main Gate, Tyndall Ave., 2nd St., 6th St., Cherry Ave., South Stadium have been designed and pricing is in progress. Golfcart charging station in Tyndall is completed.

Current Budget
$1,600,000
Projected Ultimate Budget
$1,600,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
WGI Engineering
Construction Schedule
September 2022 - June 2023
Contractor
SMS Construction, LLC

23-9657

PAS Building, Scanning Tunneling Microscope Installation

Installation of a Scanning Tunneling Microscope

Feasibility study is underway

Current Budget
$25,000
Projected Ultimate Budget
$25,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Sears Gerbo
Construction Schedule
TBD - TBD
Contractor
None

23-9658

PBC, CAMI Building

Current Budget
$150,000,000
Projected Ultimate Budget
$150,000,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

23-9636

Phoenix Mining Mineral & Natural Resources Museum Renovations

Renovation of existing Mining Mineral and Natural Resource Museum on the Capital Mall in Phoenix, AZ.

Project scope is being developed.

Current Budget
$12,000,000
Projected Ultimate Budget
$12,000,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

23-9648

PTS CatTran Project Improvements

New offices and bus maintenance facility for Parking and Transportation Services.

Construction Documents being finalized.

Current Budget
$600,000
Projected Ultimate Budget
$600,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
M3
Construction Schedule
March 2023 - May 2023
Contractor
R.W.Burkel

22-9579

Scottsdale Waterfront Phoenix Embassy Building

Fit out of existing office building for use by the University of Arizona administrative units in the Greater Phoenix area.

Construction documents have been submitted for permits.

Current Budget
$6,225,000
Projected Ultimate Budget
$6,225,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Ayers Saint Gross
Construction Schedule
September 2022 - February 2023
Contractor
McCarthy Building Companies

23-9625

Shantz Building Renovation

Renovate existing Shantz Building to update infrastructure and repurpose building programming.

Design-Build Team contract negotiations are in progress. Programming phase commencing soon.

Current Budget
$5,200,000
Projected Ultimate Budget
$65,000,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
None
Construction Schedule
February 2024 - July 2025
Contractor
None

19-9450

South Stadium Rowhouses

This College of Architecture, Planning & Landscape Architecture (CAPLA) student design-build project is providing new faculty/staff temporary housing. Five row houses are located along Seventh Street, adjacent to the South Stadium Parking Garage.

Construction is substantially complete on the third and fourth rowhouses. Construction is in progress on the fifth/final rowhouse.

Current Budget
$1,150,000
Projected Ultimate Budget
$1,150,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
CAPLA
Construction Schedule
February 2019 - September 2023
Contractor
CAPLA

17-9381

Student Success District

The new Student Success District will integrate and revitalize student services in four adjacent central campus buildings: Main Library, Weaver Science-Engineering Library, Bear Down Gym, and a new Student Services Building. The project will also include site development improvements.

Current Budget
$81,000,000
Projected Ultimate Budget
$81,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Poster Mirto McDonald
Construction Schedule
January 2019 - October 2021
Contractor
Sundt

22-9608

SUMC Building 19, Room 205 Remodeling

Remodel Room 205 in Building 19 of SUMC Building.

Project is in Pricing phase.

Current Budget
$1,400,000
Projected Ultimate Budget
$1,400,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Multistudio, Inc. (formerly Gould Evans Associates)
Construction Schedule
March 2023 - July 2023
Contractor
WE ONeil Construction Company Inc

21-9559

The Bridges, High Bay Facility

New building to support research projects requiring specialized high bay facilities to be located at The Bridges.

Current Budget
$4,750,000
Projected Ultimate Budget
$4,750,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Swaim Associates
Construction Schedule
January 2022 - November 2022
Contractor
Concord General Contracting Inc

22-9594

The Refinery, 3rd Floor Tenant Improvement

Tenant Improvements for UA Online and Continuing Professional Education. Build out to include classrooms, conference rooms, advising and administrative spaces.

Current Budget
$2,302,845
Projected Ultimate Budget
$2,302,845
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Swaim
Construction Schedule
April 2022 - August 2022
Contractor
CORE

23-9632

The Refinery, Suite 355 CAST Tenant Improvement

Shell space build out of eight offices for UA College of Applied Science and Technology satellite location.

Current Budget
$434,183
Projected Ultimate Budget
$434,183
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Swaim
Construction Schedule
September 2022 - November 2022
Contractor
CORE

19-9463

UA Global Center, Park Student Union Renovations

Renovations to former Park Student Union (PSU) will accommodate relocation and consolidation of the UA Global's functions from elsewhere on campus. The resulting Global Center will serve as a hub for international activities on Campus. The project is Initiative 4.2C4 of the UA Strategic Plan.

Phase 1 work (relocation of customer facing functions) is complete and occupied. Co-work Offices portion of Phase 2 is complete and occupied. Construction Documents for the remainder of Phase 2 (food court & dining, courtyard, and common areas) are substantially complete.

Current Budget
$9,900,000
Projected Ultimate Budget
$9,900,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
May 2019 - August 2023
Contractor
CORE Construction

22-9584

UA Global Center, Starbucks

The existing bagel shop will be renovated into a Starbucks.

Current Budget
$1,025,000
Projected Ultimate Budget
$1,025,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
BWS Architects
Construction Schedule
July 2022 - September 2022
Contractor
CORE Construction

22-9586

UAHS BSPB 2nd Floor Finish Shell Space

Fit out of existing 2nd floor shell space in the Biomedical Sciences Partnership Building for interim space for UAHS Center for Advanced Molecular and Immunotherapies (CAMI) while planning continues for the new building.

Schematic design documents are underway.

Current Budget
$18,500,000
Projected Ultimate Budget
$18,500,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
None
Construction Schedule
February 2023 - September 2023
Contractor
None

20-9512

UAHS Building 201 Basement Renovation, UAHS Sleep Research Center

Renovation of existing space in the basement to provide a Sleep Research Center - funding being provided by the National Institutes of Health.

Current Budget
$5,045,665
Projected Ultimate Budget
$5,045,665
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Sears Gerbo Architecture
Construction Schedule
December 2021 - February 2023
Contractor
Kitchell Contractors, Inc. of Arizona

23-9654

University Services Building, Unit Relocations

Interior renovations to consolidate university departments

Programming effort in progress.

Current Budget
$300,000
Projected Ultimate Budget
$6,000,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Sears Gerbo
Construction Schedule
April 2023 - October 2023
Contractor
None

23-9639

Visual Arts Graduate Research Laboratory renovation

Reconfigure spaces inside the building to provide additional studios that can be assigned to faculty and visiting artists.

Initial design is underway.

Current Budget
$150,000
Projected Ultimate Budget
$2,200,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
May 2024 - August 2024
Contractor
CORE Construction