17-9369

1700 E. Broadway Building 480 Refurbishment/Repair

Refurbish and repair a 2-story, off-campus office building to provide administrative space for UA departments relocating from the UA Health Sciences medical campus as part of the UA/Banner University Medical Center initiative.

Current Budget
$1,277,000
Projected Ultimate Budget
$1,277,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Dave Diebold Architect
Construction Schedule
July 2017 - November 2017
Contractor
W.E. O’Neil Construction Co.

18-9389

655 N Alvernon Building 491 FFE Procurement and Installation

Office furnishings for the various occupant groups.

Tri U vendor: Corporate Interior Systems. Furniture floor plans, isometrics, finishes and installation plans underway.

Current Budget
$1,005,000
Projected Ultimate Budget
$1,005,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Swaim Associates
Construction Schedule
TBD - TBD
Contractor
N/A

16-9340

655 N. Alvernon Building 491 Refurbishment/Repair/Renovation

Refurbish/repair/renovate this off-campus building as required to provide administrative space for University of Arizona Health Sciences programs that will be relocating from the UAHS medical campus as part of the UA/Banner University Medical Center initiative.

Interior walls complete. Electrical, mechanical, ceilings and finishes underway. Site work in progress.

Current Budget
$4,995,000
Projected Ultimate Budget
$4,995,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Swaim Associates, LTD
Construction Schedule
July 2017 - November 2017
Contractor
KappCon Construction

17-9368

AME Building Room N341 Renovation

Renovation of Lab N341 to house a Mach 4 wind tunnel.

Demolition is complete. Tank is fabricated and ready for installation.

Current Budget
$205,000
Projected Ultimate Budget
$205,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
PD&C
Construction Schedule
September 2017 - December 2017
Contractor
Sun Mechanical

16-9316

Arizona Public Media - Renovations

Renovation of the radio operations wing of the AZPM broadcasting facility with the intent of upgrading and increasing production studio space. This part of the project was delivered in two phases in order to reduce disruptions to broadcast operations during construction. Phase Three includes improvements to the Televisions Master Control Room and minor millwork improvements.

Current Budget
$592,000
Projected Ultimate Budget
$617,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design & Construction
Construction Schedule
September 2016 - October 2017
Contractor
CORE Construction

16-9330

Arizona Stadium Renovation

The initial phases of renovation will be on the east side of the stadium, including work on the ground level concourse, student seating area (the ZonaZoo), and the southeast entrance.

The feasibility study was completed, evaluating the cost and impact of renovating the east, west and south sides of the football stadium: including improving the infrastructure, safety, code upgrades, circulation, restrooms, concessions and fan amenities. Design is in-progress for the initial east side renovations.

Current Budget
$3,438,000
Projected Ultimate Budget
$150,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
J E Dunn w/ Populous & Swaim
Construction Schedule
January 2018 - August 2018
Contractor
J E Dunn Construction Company

17-9377

Biological Science West, 4th Floor Lab Renovation

Renovation of labs for new occupant relocating from old Chem.

Design has started

Current Budget
$130,000
Projected Ultimate Budget
$130,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Planning Design & Construction
Construction Schedule
TBD - TBD
Contractor
None

14-9230

Biomedical Sciences Partnership Building

This facility is located on the Phoenix Biomedical Campus and includes research space, wet and dry laboratories, and related core facilities.

Current Budget
$136,100,000
Projected Ultimate Budget
$136,100,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
December 2014 - January 2017
Contractor
D P R / Sundt (A Joint Venture)

12-9134

Bioscience Research Laboratories

The BSRL will provide research facilities to support interdisciplinary research in many health science disciplines. This new facility will encourage collaborative translational research that will advance understanding of the molecular basis of human health, aging and disease.

Installation of mechanical, electrical, and plumbing systems is nearing completion on all levels. Sheetrock is complete and painting is well underway. The building exterior envelope work is underway with glass installation nearing completion, and brickwork moving quickly through all levels. The site hardscape and landscaping is progressing. And finish cabinetry and audio visual system installation is underway.

Current Budget
$107,500,000
Projected Ultimate Budget
$107,500,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Zimmer Gunsul Frasca Architects, LLP
Construction Schedule
December 2015 - December 2017
Contractor
D P R Construction Inc

16-9337

BSRL Basement Shell Tenant Improvement

This project will build out shell space in the basement of the new BSRL building for Health Sciences CGRI instrumentation equipment.

The space is dry walled, and the final work in the ceilings is finishing up. Painting and flooring have begun.

Current Budget
$4,500,000
Projected Ultimate Budget
$4,500,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
ZGF Architects with BWS
Construction Schedule
December 2016 - December 2017
Contractor
DPR Construction

15-9273

C.A.T.S. Academic Center

The Arizona Wildcat Academic Center provides tutoring and other academic support services for all UA student athletes. The project also includes two polar plunge pools for athlete's conditioning and muscle recovery following workouts.

Current Budget
$7,550,000
Projected Ultimate Budget
$7,550,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
AECOM Technical Services
Construction Schedule
February 2016 - August 2017
Contractor
Mortenson Construction

18-9397

CAPLA West, 2nd and 3rd Floor Remodel

In order to improve space utilization and provide facilities for increased program growth, CAPLA plans to reconfigure the current CAPLA West spaces for improved efficiency with a view to increase student studio and research spaces and also provide active learning and collaborative classrooms.

Project under review by UA Administration.

Current Budget
TBD
Projected Ultimate Budget
$900,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

16-9341

College of Law, Grand Staircase Display

In recognition of Richard D. Grand contributions, the College of Law is naming their main (grand) staircase in his honor. The project will construct a Memorial Exhibit Case that will house Richard D. Grand memorabilia.

Display case framed into existing wall is complete. Graphics on stair and wall display case are complete. Freestanding display case for the donor's bust is on order.

Current Budget
$89,800
Projected Ultimate Budget
$89,800
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Gould Evans
Construction Schedule
July 2017 - November 2017
Contractor
Division II

17-9362

College of Pharmacy Skaggs Building Addition and Renovation

The College of Pharmacy intends to continue its innovation and excellence in research, practice and education and make a substantial impact on improving the health of people of Arizona and around the world. This project will provide the College with both new and renovated state-of-the-art research lab facilities to ensure its growth and capacity to adapt to the dynamic and changing fields in pharmaceutical sciences.

The Design Development phase is in-progress.

Current Budget
$1,320,000
Projected Ultimate Budget
$26,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
G L H N Architects And Engineers
Construction Schedule
April 2018 - December 2019
Contractor
DPR Construction

16-9334

COM-Phoenix (Administration) Bldg 3002, Eller Administrative Suite Remodel

Remodel of 2nd floor east half of Building 1 on the Phoenix Biomedical Campus to accommodate new administrative offices for Eller Executive and Evening MBA programs.

Current Budget
$615,292
Projected Ultimate Budget
$615,292
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
SmithGroupJJR
Construction Schedule
September 2016 - December 2016
Contractor
DL Withers

55-2944

DAS Arizona Stadium Antenna Upgrades

Expansion of the Distributed Antenna System (DAS) in Arizona Stadium is being conducted in three stages or components. This component involves the relocation and expansion of antennas in Arizona Stadium

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Boingo
Construction Schedule
May 2017 - August 2017
Contractor
EWS

55-2942

DAS Expansion (Boingo) at Arizona Stadium

Expansion of the Distributed Antenna System (DAS) in Arizona Stadium is being conducted in three stages or components. This component involves the expansion of the head end equipment room and associated infrastructure improvements by Boingo.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Boingo
Construction Schedule
May 2017 - August 2017
Contractor
Boingo

55-2943

DAS Expansion (T-Mobile) at Arizona Stadium

Expansion of the Distributed Antenna System (DAS) in Arizona Stadium is being conducted in three stages or components. This component involves the fit out of new equipment by T-Mobile in the expanded head space.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Boingo
Construction Schedule
May 2017 - August 2017
Contractor
EWS

03-8526

Environment & Natural Resources 2 (ENR2)

This new facility at 1064 E. Lowell St.(ENR2) east of the DeConcini ENRB1 furthers interdisciplinary research in earth, environmental, natural resources, math and related sciences. Included are faculty offices, conferencing, support spaces with related research/instructional dry laboratories and work space. A large classroom auditorium meets the critical need to teach an increasing number of students.

Current Budget
$75,000,000
Projected Ultimate Budget
$75,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
June 2013 - May 2015
Contractor
Hensel Phelps Construction Company

13-9182

Health Science Education Building, Finish Shell Space

This Tenant Improvement project in the Health Sciences Education Building will include a regional Simulation Center, completion of a Lecture Hall, administrative space, a Presidential Suite and the possible inclusion of classroom/Learning Studio space. Projects 13-9182 (HSEB, Finish Shell Space), 13-9206 (HSEB Finish Shell Space UA), and 13-9207 (HSEB Finish Shell Space NAU) will be covered under this description.

Current Budget
TBD
Projected Ultimate Budget
$17,900,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
January 2014 - July 2014
Contractor
None

09-8900

Health Sciences Education Building

The building on the Phoenix Biomedical Campus (PBC), 435 N. 5th Street, Phoenix 85004, includes flexible classrooms and state-of-the-art educational facilities, such as, simulation laboratories, gross anatomy facilities, preclinical training, learning resource center, student services and faculty office administrative space.

The HSEB creates an iconic identity for the University of Arizona School of Medicine on the Phoenix Biomedical Campus and responds to its urban locale and desert environment. The Arizona desert climate and need for reduced energy consumption informed much of the design, from the way the building is sited at its location to the type of fenestration and the innovative cooling methods used. Inspired by the iconic canyon formations found throughout Arizona, the façade reinterprets stratified earth layers revealed over time as a copper sunscreen protecting the exterior building enclosure from direct solar exposure. Akin to the natural forces that shape the Earth’s geology, the copper skin is fissured, formed, bent, pressed, and perforated, creating beauty from a functional building need. The architectural design promotes physical connectivity to the downtown Phoenix community with indoor and outdoor spaces that encourage interaction.

Current Budget
$135,998,801
Projected Ultimate Budget
$135,998,801
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
July 2010 - July 2012
Contractor
D P R / Sundt (A Joint Venture)

13-9193

Health Sciences Innovation Building

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

Structural topping out completion was celebrated on Nov 17. East side curtain wall and terra cotta installation is underway. Interior wall framing and MEP rough-in are underway on lower floors. All air handlers have been installed. Secure corridor construction to MRB is progressing.

Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
CO Architects
Construction Schedule
June 2016 - July 2018
Contractor
Kitchell

18-9388

Hillenbrand Aquatic Center Improvements

The Hillenbrand Aquatic Center Swimming Pool, Pump/Filtration Room and Chemical Room is due for a life cycle replacement. The pools structural integrity is severely degraded and the mechanical filtration system is corroded and unsafe. The new pool will not only be significantly longer (70m) but will have state-of-the-art technology for practicing and for competition. The pool will also accommodate multiple bulkheads. The Old Dive Pool will be demolished to create the space needed for the longer pool.

Fee negotiations with top ranked D-B firm is ongoing.

Current Budget
$25,000
Projected Ultimate Budget
$15,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Architekton
Construction Schedule
May 2018 - December 2018
Contractor
CORE Construction, Inc.

17-9382

Hillenbrand Softball Stadium Renovations

The proposed project would renovate portions of the existing softball stadium including the following potential items: sun shading, create new fan amenities in seating areas, press box renovations, upgrade dugouts, and replace the backstop netting system.

The design process is underway, as is the RFQ process for selection of a CM@Risk.

Current Budget
$500,000
Projected Ultimate Budget
$8,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Swaim
Construction Schedule
June 2018 - January 2019
Contractor
None

14-9227

HSEB - NAU Occupational Therapy Area Improvements

Project consists of the remodel of the existing occupational therapy rooms in the Health Science Education Building to accommodate new equipment that is being purchased by Northern Arizona University.

Current Budget
$170,716
Projected Ultimate Budget
$170,716
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2014 - July 2014
Contractor
None

17-9344

ICA Hi Corbett Renovations

Upgrades to the baseball facilities include a new backstop netting system, replacing some of the spectator seating, and interior renovations to the team clubhouse and locker room. Project scope increased to now also include the new Terry Francona Hitting Facility.

Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Breckenridge Group
Construction Schedule
January 2017 - October 2017
Contractor
Concord General Contracting

18-9390

ICA Indoor Sports Center

The proposed new building would provide safe all-weather practice for football and other sports. The multi-use facility is envisioned to benefit multiple sports and could also possibly serve as an additional game day venue.

The RFQ process for selection of a Design-Build team is nearing completion.

Current Budget
$20,000
Projected Ultimate Budget
$15,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
March 2018 - January 2019
Contractor
None

16-9309

Kuiper SEM/TEM Phase B

The goal of the expansion of the SEM/TEM Imaging Core is to accommodate two existing Hitachi SEMs presently located in the Marley Chemistry building, and future advanced technology imaging equipment. It will also provide interactive meeting space for researchers from the Lunar and Planetary Laboratory as well as visiting users from UA and industry partners. Specifically the expansion will achieve the following goals: Provide state of the art imaging capability to LPL, UA and outside users; Provide office space for technicians assigned to the Imaging Core; Provide a modular and flexible environment to allow for a variety of imaging instruments

Current Budget
$1,302,000
Projected Ultimate Budget
$1,302,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Sears Gerbo
Construction Schedule
September 2016 - January 2017
Contractor
R W Burkel

18-9393

La Aldea Residence Hall Renovations

The apartment units in the Graduate Housing facility will be renovated, including finishes, casework and fixtures.

The initial phase will be the renovation of one apartment, to serve as a prototype for the balance of the project.

Current Budget
$50,000
Projected Ultimate Budget
$50,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Breckenridge Group
Construction Schedule
January 2018 - August 2018
Contractor
Lloyd Construction

16-9299

Maricopa Agricultural Center, Install Field Gantry

This project involves the construction of a foundation system to support a 28m x 218.5m field scanner gantry instrument at the Maricopa Ag. Center. Project also includes the installation of main electrical and telecom service.

Current Budget
$1,020,000
Projected Ultimate Budget
$1,020,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Structural Concepts
Construction Schedule
October 2015 - March 2016
Contractor
Div. II Construction

17-9358

Maricopa Hall Renovations

Renovations to the nearly century old residence hall will include conversion of sleeping porches into student rooms, modifications to student room storage, replacement windows in lounges, installation of occupancy sensors, and replacement flooring in student rooms and corridors.

Current Budget
$1,890,000
Projected Ultimate Budget
$1,890,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
May 2017 - August 2017
Contractor
Lloyd Construction

17-9360

McClelland Hall Lab 214 Renovation

In order to enhance the teaching delivery and, improve the learning experience, the Eller College of Management is renovating McClelland Hall Lab 214 by converting the tiered lecture style seating into a flexible Classroom space with mediated interaction.

Current Budget
$831,000
Projected Ultimate Budget
$831,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Gould Evans
Construction Schedule
June 2017 - September 2017
Contractor
Division II

18-9385

McKale Memorial Center, Locker Room Suite 170 Remodel

In order to improve student athlete support areas, Intercollegiate Athletics (ICA) will be adding 4 new locker rooms and remodeling 2 existing locker rooms. The remodeled spaces will be complete with lounge/team areas, kitchenette, etc.

100% CD is nearing completion.

Current Budget
$300,000
Projected Ultimate Budget
$1,900,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Swaim Associates, Ltd
Construction Schedule
April 2018 - August 2018
Contractor
Concord General Contracting

55-2963

Mt. Lemmon OWL Telescope

Steward Observatory has requested PDC's assistance in facilitating the installation of a new enclosure to house a new 0.5M OWL telescope. Project is privately funded and will be operated by the Korean Astronomy Space Sciences Institute (KASI).

Current Budget
$5,754
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design & Construction
Construction Schedule
February 2016 - November 2016
Contractor
Kappcon

16-9323

Multiple Parking Garage Maintenance Repairs 2017

In 2013, a "Conditions Evaluation and Preventative Maintenance Report" was issued for all of the parking garages on Campus including the Highland Avenue, Park Avenue, Tyndall Avenue, Sixth Street, and Main Gate Garages. This project will address all of the needs that were identified in that report to repair and maintain these five garages in 2017. The actual repairs and maintenance will be done in the summer of 2017. This work will assure that these five garages are maintained in good condition and remain serviceable for the foreseeable future.

Current Budget
$700,000
Projected Ultimate Budget
$700,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Desman Associates
Construction Schedule
May 2017 - October 2007
Contractor
None

12-9135

North Campus Infrastructure

North Campus Infrastructure is a multi-stage, multi-element project which will expand the University's existing infrastructure including, but not limited to mechanical; electrical; telecommunications utility distribution systems; central plant heating, chilled water and potable water production; sewer and surface drainage to support the new Bioscience Research Lab Building, the proposed Engineering Innovation Building and future campus growth.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2015 - May 2016
Contractor
Sundt Construction Inc

17-9364

Parking Lot Improvements 2017

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8178 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Phase 1 - Lots 2152, 5073 and 5067 have been re-paved, striped and opened. The single one way bike path for east bound bike traffic along the south side of 5067 is completed and in use. Lots 8178 / 8179 have been expanded and opened. The pedestrian walkway between 6th and 7th Streets on the east side of Sitton Field is open and in use. Phase 2 - Design of Lot 3140 is being finalized.

Current Budget
$612,000
Projected Ultimate Budget
$676,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
Eagle Rock and DFDG/GLHN
Construction Schedule
May 2017 - December 2017
Contractor
Eagle Rock Excavating and McCarthy

18-9391

Pima County Court House, Gem and Mineral Museum Relocation

Explore the feasibility of the relocation of the UA Gem and Mineral Museum to the Old Pima County Courthouse. Lower Level 9,200sf - Research Lab, Community and Storage Level 1 (Main Level) 11,700sf- Gem and Mineral Museum Exhibits.

Project is in Administrative review. Exhibit Design schedule has been developed. Exhibit Content is being developed.

Current Budget
$25,000
Projected Ultimate Budget
$25,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Pima County (Poster Frost Mirto)
Construction Schedule
July 2018 - October 2019
Contractor
Pima County

17-9378

School of Arts Letterpress Program Relocation

Evaluate potential relocation sites for the University's Fine Arts Letter Press Program.

Phase 1 renovation work is nearing completion. Phase 2 renovation work will start in May 2018.

Current Budget
$425,000
Projected Ultimate Budget
$425,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
GLHN
Construction Schedule
September 2017 - July 2018
Contractor
W. E. O'Neil

08-8847

Solar/Sustainable Initiatives

A solar/sustainable initiative is underway that is being facilitated through the University's partnership with AMERESCO to advance solar technology awareness on campus and throughout the community. Through this initiative solar installations are planned for Second Street Garage, Student Recreation Center, McClelland Hall, McClelland Park, Hillenbrand Aquatic Center, Red Rock Ag Center, Campus Ag Center, Controlled Environmental Ag Center, West Campus Ag Center, Ville Del Puente Res Hall, and Posada San Pedro Res Hall.

Current Budget
$360,500
Projected Ultimate Budget
$360,500
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
AMERESCO
Construction Schedule
July 2009 - July 2012
Contractor
AMERESCO

13-9168

South Stadium Parking Structure

This five-level parking structure with 915 parking spaces is conveniently located south of 6th Street near student housing and athletic facilities. The 6th St. & Warren Ave. intersection was redesigned to align with National Championship Drive to the north and includes a new traffic signal, sidewalks and bike lanes which are expected to greatly improve traffic flow throughout the area and increase efficiency and safety.

Current Budget
$22,000,000
Projected Ultimate Budget
$22,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
DFDG
Construction Schedule
December 2016 - August 2017
Contractor
McCarthy Building Companies

17-9376

Southwest Center, Building 375, 375A & 375B Repairs

The College of Social and Behavioral Sciences intends to conduct roofing repairs and remedial work on these three buildings which are part of their Southwest Center program.

Interior/remedial repairs are in progress.

Current Budget
$250,000
Projected Ultimate Budget
$250,000
Project Manager
Facilities Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
June 2017 - December 2017
Contractor
None

16-9321

Student Recreation Center, Locker Room Remodel

This is a comprehensive locker room remodel to achieve greater inclusivity for all Recreation Center patrons, as well as update the 25 year old facilities with more contemporary design features and finishes.

Current Budget
$4,945,000
Projected Ultimate Budget
$4,945,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Breckenridge Group
Construction Schedule
March 2017 - August 2017
Contractor
Lloyd Construction

17-9381

Student Success District

The new Student Success District will integrate and revitalize student services in four adjacent central campus buildings: Main Library, Science and Engineering Library, Bear Down Gym, and a new Student Services Building. The project will be delivered in two phases, and will also include site development improvements.

Programming phase is underway.

Current Budget
$3,000,000
Projected Ultimate Budget
$71,000,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
Poster Frost Mirto
Construction Schedule
July 2018 - June 2020
Contractor
Sundt

17-9353

Student Union Memorial Center, Chick-fil-A Relocation

In order to improve student food services, the Student Union Memorial Center is renovating by upgrading and expanding the food space for Chick-fil-A .

Current Budget
$500,000
Projected Ultimate Budget
$500,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Merry Carnell Schlecht
Construction Schedule
July 2017 - September 2017
Contractor
CORE Construction

55-2898

SUMC Steak and Shake Tenant Improvements

This is a tenant improvement project. MSE Branded Foods is a SUMC tenant who is constructing a Steak N' Shake Restaurant in the old Burger King space. They have contracted with WE O'Neil to complete this work. PDC is providing oversight and inspection.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
July 2017 - August 2017
Contractor
None

18-9399

SUMC, Room 226A Starbucks Remodel

In order to improve student food service and retail experience, UABookStores will be reconfiguring and expanding the existing Starbucks shop.

Project under review by UA Administration.

Current Budget
TBD
Projected Ultimate Budget
$250,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
July 2018 - July 2018
Contractor
None

15-9264

SUMC-Bookstore, Room 202 Remodeling

Remodel the main level to update the facility to better serve customers and to reflect the current retail marketing trends.

Current Budget
$1,000,000
Projected Ultimate Budget
$1,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Colkitt & Co Architects
Construction Schedule
May 2016 - July 2016
Contractor
W.E. O'Neil Construction Co. Inc.

10-9001

UA Cancer Center-Phoenix - Phase I

This new facility provides the highest quality cancer research and care with an evidence-based, multi-disciplinary model, along with the modern technologies, and a compassionate patient-centered approach. The building is located at 625 N. 6th St, on the northwest corner of Fillmore and Seventh Streets on the downtown Phoenix Biomedical Campus.

Current Budget
$100,000,000
Projected Ultimate Budget
$100,000,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsel Frasca
Construction Schedule
January 2013 - May 2015
Contractor
Hensel Phelps Construction Co.

18-9395

UA Honors Village

The University of Arizona has entered into a Public Private Partnership agreement with American Campus Communities to develop, design and construct the UA Honors Village, a multi-building complex consisting of a 1035 bed Honors Dorm, that also includes academic space and food services, a Recreation Center and a 4 story, 370 space Parking Structure.

Contractor is mobilizing on site.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
November 2017 - July 2019
Contractor
None

16-9339

UAHS Border Health, Building 426 Renovation

Renovation of leased building to provide office and clinic space to accommodate the UAHS Border Health Initiative program in Nogales, Arizona.

Current Budget
$485,000
Projected Ultimate Budget
$485,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Dave Diebold Architect
Construction Schedule
January 2017 - February 2017
Contractor
Lloyd Construction Co., Inc.

17-9363

UAHS Building 201 Renovations

As part of the University of Arizona/Banner Health initiative, a number of UAHS departments need to be relocated. To facilitate this phased relocation effort, existing space on multiple levels in Building 201 will be renovated to provide the administrative and ancillary support associated with UAHS departments.

Design Development documentation is being prepared.

Current Budget
$1,620,000
Projected Ultimate Budget
$14,500,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
None
Construction Schedule
January 2018 - April 2018
Contractor
None

16-9313

UITS Infrastructure Upgrade

This project is to upgrade the existing IT Data Network Hubs for a systems upgrade to 100GB network.

Current Budget
$297,000
Projected Ultimate Budget
$297,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
UA Planning Design and Construction
Construction Schedule
March 2016 - May 2016
Contractor
Sturgeon ELectric

17-9365

University Services Building 3rd Floor Renovation

Existing office space on the 3rd floor NE corner of USB Building has been converted into a functional space for University Analytics & Institutional Research operations.

Current Budget
$695,000
Projected Ultimate Budget
$695,000
Project Manager
Facilities Project Manager
Phase
Occupancy
Design Professional
Dave Diebold Architects
Construction Schedule
June 2017 - September 2017
Contractor
D L Withers

55-4032

USA East Parking Lot / 6th Street Underpass

The Downtown Links project that the City of Tucson is constructing for the 6th Street underpass of the Union Pacific Railroad will require the realignment of the entrance to the east parking lot and a new parking lot layout which includes new parking lot lighting.

Design of the parking lot lighting and relocation of the gate operators are complete. Construction to begin Summer 2016.

Current Budget
$3,731
Projected Ultimate Budget
$4,000
Project Manager
Facilities Project Manager
Phase
Design
Design Professional
UA Planning Design & Construction
Construction Schedule
TBD - TBD
Contractor
None