PROJECT INFORMATION

Andrew Weil Center for Integrative Medicine

Description

This project will develop a new facility for the Andrew Weil Center for Integrative Medicine (AWCIM) to centralize their operations in a physical building and landscape environment that supports their philosophy of healthy work environments.

Status

Masonry walls (CMU) and mechanical, electrical, plumbing rough-in is in progress. Structural steel roof framing at the multi-purpose building is complete and roof decking starting. Main office building structural steel erection is underway.

Project Number
19-9472
Building Number(s)
233
Current Budget
$23,000,000
Projected Ultimate Budget
$23,000,000
Project Manager
Construction Project Manager
Construction Schedule
May 2022 - October 2023
Contractor
DPR Construction
Phase
Construction
Design Professional
Line and Space, LLC
Delivery Method
CMR
GSF
29,400
VIEW SCHEDULE